India's first bullet train section - a 50km stretch between Bilimora and Surat in Gujarat - will be completed in August 2026, Railways Minister Ashwini Vaishnaw said Wednesday, as he announced multiple plans to overhaul the country's rail network.
Mumbai Ahmedabad Bullet Train Project: Larsen & Toubro (L&T) emerged as the lowest bidder for the design and construction of an 8 km viaduct and the Vadodara station
Mumbai-Ahmedabad Bullet Train: To speed up the construction of viaduct for the country's first bullet train corridor, NHSRCL is adopting the full span launching method.
Mumbai-Ahmedabad Bullet Train: NHSRCL opened financial bids for the construction and design of an 18 km viaduct and railway stations at Ahmedabad and Sabarmati
Mumbai-Ahmedabad Bullet Train: With activities such as segments at casting yards, pier reinforcement work etc being undertaken by authorities - the bullet train project is currently under various stages of construction.