As structures at the former power plant in Springdale continue to be demolished, except the boiler house, some people might have noticed another structure being erected: a fence around the property on Porter Street. “That fence that’s on Porter is a security fence when, eventually, the administration building and wall
As the fate of the boiler house at the former power plant in Springdale is hung up in the courts, crews continue to take down other buildings at the site. “Generally speaking, we’ve been making progress on some of the other buildings throughout the site,” said Scott Reschly, vice president
Attorneys representing the residents seeking to block an implosion of the boiler house say they’re “thrilled” with a recent court decision that sets procedure before the demolition can be considered. “The court determined that the plaintiffs were all harmed by the June 2 implosion, suffering harm to their homes, damage
An absorber tank at the former power plant in Springdale was knocked down Thursday afternoon. The action at the plant, formally called the Cheswick Generating Station, is part of the remediation efforts at the site, said Scott Reschly, vice president of Charah Solutions. Cheswick Plant Environmental Redevelopment Group, a subsidiary
A Sept. 22 implosion date has been set for the boiler house building at the former Cheswick Generating Station plant in Springdale. Scott Reschly, vice president of operations for Charah Solutions, an environmental remediation firm and the property’s owner, said Friday the demolition of the boiler house building is planned