The owner of the former power plant in Springdale has 21 days to show how an Allegheny County court erred in granting a preliminary pause to imploding the boiler house at the site. Allegheny County Judge John T. McVay Jr. ordered Tuesday that Charah Solutions has 21 days to file
Springdale planners on Wednesday pressed pause before making a recommendation on renewing a demolition permit at the borough’s former Cheswick Generating Station. Cheswick Plant Environmental Redevelopment Group, a subsidiary of property owner Charah Solutions, and Grant Mackay Co. requested renewal of the demolition permit, which expires Jan. 17. “The next
Attorneys representing the residents seeking to block an implosion of the boiler house say they’re “thrilled” with a recent court decision that sets procedure before the demolition can be considered. “The court determined that the plaintiffs were all harmed by the June 2 implosion, suffering harm to their homes, damage
Attorneys representing the Springdale residents seeking to stop an implosion of the boiler house at the former Springdale power plant question why the property owner’s legal counsel wants to prohibit photographs taken during a site visit as evidence to be considered in the hearing. Attorney John Kane, who represents the
A Texas-based toxicologist testified Tuesday that health complaints reported by some Springdale residents following the June implosion of two towering smokestacks at the former power plant there are consistent to exposure of materials and fibers from the implosion. But the defense attorneys for the landowner and demolition company attempted to