comparemela.com

Latest Breaking News On - Pacific electric company - Page 1 : comparemela.com

Transcripts For SFGTV 20141117

May be acted upon by a single roll call vote of the commission. There will be no separate discussion of these items unless a member of the commission, the public, or staff so requests removed from the consent calendar and considered as a separate item at this or a future hearing. 8 a approve amendment one and execute two amendments not to exceed 25 thirtyfour cents thousand dollars each and execute not to exceed to 49 thousand he each and for the time extension the approve increasing the amendment by 250,000 c accepting the modification extending the contract by 3 hundred and 49 consequent calendar days and authorize the final payment to the contract 8 d approving the contract 48 russ johnson not to exceed 49 million and the work contract w did 4,745,200,000,000 plus f accept contract w w 5 hundred and approve the modifications increasing the contract by 4 hundred and 19 thus plus with a time extension of 49 calendar days and g accept contract and paragraph the modifications for 70 sce

Transcripts For SFGTV 20141113

Execute two amendments not to exceed 25 thirtyfour cents thousand dollars each and execute not to exceed to 49 thousand he each and for the time extension the approve increasing the amendment by 250,000 c accepting the modification extending the contract by 3 hundred and 49 consequent calendar days and authorize the final payment to the contract 8 d approving the contract 48 russ johnson not to exceed 49 million and the work contract w did 4,745,200,000,000 plus f accept contract w w 5 hundred and approve the modifications increasing the contract by 4 hundred and 19 thus plus with a time extension of 49 calendar days and g accept contract and paragraph the modifications for 70 scent days and authors the payment for the contract h the Construction Costs for the contract in the amount of 4 hundred thousand and the duration of 27 days and authorize amazing maximum amount i approve the clarification and the award of the contract number in the amount of one Million Dollars 5 hundred plus an

Transcripts For SFGTV 20141113

Sass say the customers are doing well, well chief in 2015 its for october 1st through cement 30th were going to be watching our precipitation production and in the event that in springtime were following somewhere around the hydrologic conditions of 2007 well maintain the 10 percent reduction and have carry over storage so well still meet our demands if we have a year like 1997 in terms of that well want to take additional action if you go it down we e done we cant take action well be following the precipitation we like to wait for the snow pack and how much we need to anticipate in run off. So i hope i guess april if not before that 20 percent alternative analysis will be pretty primed and read for us to have the implementations pretty big. Yeah. Any other comments thank you very much. So the next item is a querulous update amelia will start the presentation. Good afternoon, members of the commission amelia cruz assistant general manager of the structure dpa will give the body of the

Transcripts For SFGTV 20141117

Stone based construction in the lower right of the photo has begun and you can see the projection with the dam takes place and couple of photos here this is a verify looking down stream with the concrete replacement of the left abatement this is to replace landslide materials that had to be removed and use the concretes for the foundation interests about 10 thousand cubic yards of concrete for the rack replacement this backflow concrete its hard to see the scale from the photos but that is about 35 feet thick and a new 10 thousand yards of concrete this next photo shows a closeup this is looking down stream that wall is 40 feet tall it is consistent of 50 thousand yards of concrete and the spill will be 50 feet long to date weve placed 10 thousand square feet in the walls this photo shows the left abatement and the construction from the other side of the veil from the right side you see the height that have that above the spillway and the construction continues you also see the red dru

Transcripts For SFGTV 20141124

Separate item at this or a future hearing. 8 a approve amendment one and execute two amendments not to exceed 25 thirtyfour cents thousand dollars each and execute not to exceed to 49 thousand he each and for the time extension the approve increasing the amendment by 250,000 c accepting the modification extending the contract by 3 hundred and 49 consequent calendar days and authorize the final payment to the contract 8 d approving the contract 48 russ johnson not to exceed 49 million and the work contract w did 4,745,200,000,000 plus f accept contract w w 5 hundred and approve the modifications increasing the contract by 4 hundred and 19 thus plus with a time extension of 49 calendar days and g accept contract and paragraph the modifications for 70 scent days and authors the payment for the contract h the Construction Costs for the contract in the amount of 4 hundred thousand and the duration of 27 days and authorize amazing maximum amount i approve the clarification and the award of t

© 2024 Vimarsana

vimarsana © 2020. All Rights Reserved.