The Black Creek Bridge replacement project is moving forward. Espanola council has unanimously agreed to have the final detailed design plans completed for $208,000. This process is expected to take 17 weeks and construction is estimated at 12-16 weeks. It is anticipated that the full cost of the design and construction can be 100% funded by the Ontario Community Infrastructure Funding allocations as there are approximately three years outstanding for a total of $819,500. This project will also fall under the 2021 municipal budget. Background: Black Creek bridge was rehabilitated in 2006. It should be noted that only light repairs could be completed on the cribbing and that the steel