Crews from Robert B. Our have been working to complete sewer main installations, lateral connections, paving and work at the wastewater recovery facility over the last several months.
Work on sewer installations in the Summerwood Condominiums is expected to begin in the coming week. Sandy Tripp of the consultant GHD said construction is moving along as scheduled with
SummerWood Condominiums owners will be responsible for paying 70 percent of a 70/30 apportionment split with the Town of Mashpee for a betterment to install a sewer main to connect
The Mashpee Sewer Commission scheduled a betterment hearing for SummerWood Condominiums on Route 28, which is one of the two betterment areas in the first phase of the townwide sewer
The Massachusetts Commission Against Discrimination found probable cause of racial discrimination in a complaint against the board of trustees of Summerwood Condominium Trust following an investigation into allegations surrounding a