Chief Secretary Sanjeev Kaushal directed the power utility to expedite the relocation of HT/LT lines and provide 33 KV power connection for the plant’s site from an alternative source in order to ensure uninterrupted power supply to the project.
Providing an update on the project’s progress, Project Director, GHAVP, Niranjan Kumar Mittal said, “Seventy-four per cent of the ground improvement work has been completed."
Chandigarh: The first unit of the nuclear power plant in Haryana's Fatehabad district is likely to commence operations in June 2028. The information was
The first unit of the nuclear power plant in Fatehabad district's Gorakhpur village is likely to commence operations in June 2028, according to an official statement issued here on Monday.
Providing an update on the project’s progress, project director, GHAVP, Niranjan Kumar Mittal said that 74% of the ground improvement work had been completed