Rocked by results of a recently completed shipbuilding study lambasting progress on new aircraft carriers, submarines and other major US Navy (USN) programmes, USN Secretary Carlos Del Toro is looking elsewhere for advice and examples to imp.
Following the US Navy (USN) decision to cut an expected Virginia-class attack submarine (SSN) from its proposed Fiscal Year (FY) 2025 budget proposal, Chris Kastner, the president and CEO of submarine builder HII, has called for the USN to m.
Following the US Navy (USN) decision to cut an expected Virginia-class attack submarine (SSN) from its proposed Fiscal Year (FY) 2025 budget proposal, Chris Kastner, the president and CEO of submarine builder HII, has called for the USN to m.
Shipbuilders for US Navy (USN) programmes had braced for a growing work demand signal before the onslaught of the Covid-19 pandemic, but the pandemic's impacts exacerbated the challenges of that growing manufacturing need, according to Chris.
Major US Navy (USN) shipbuilding programmes are running one to three years behind schedule due in a large part to the lack of a sufficient workforce and supply-chain disruptions, according to a 45-day shipbuilding review of these programmes .