comparemela.com

Latest Breaking News On - Chelsea curves - Page 2 : comparemela.com

Construction Update: Chelsea Curves Construction Look-Ahead Through May 1 – Chelsea Record

This is a brief overview of construction operations and traffic impacts for the Tobin Bridge/Chelsea Curves Rehabilitation Project. MassDOT will provide additional notices as needed for high-impact work, temporary ramp and street closures, and changes to traffic configurations beyond those described below. Route 1 Southbound Lane Taking (04/12-05/07) •From Monday, 4/12, through Friday, 5/07 Route 1 Southbound where it passes through the Chelsea Viaduct portion of the combined Tobin Bridge/Chelsea Curves Rehabilitation Project will experience 24/7 closure of the right lane. The two other lanes will remain open throughout the closure period during peak travel times.  •The right lane closure will assist in completing work in removing temporary asphalt, waterproofing, milling and paving, and stripping the roadway.

Construction look-ahead through March 6 – Chelsea Record

This is a brief overview of construction operations and traffic impacts for the Tobin Bridge/Chelsea Curves Rehabilitation Project. MassDOT will provide additional notices as needed for high-impact work, temporary ramp and street closures, and changes to traffic configurations beyond those described below. ROUTE 1 TRAFFIC IMPACTS ROUTE 1 NORTHBOUND: Approaching the Tobin Bridge from Boston, the work zone begins in the right lane. 2 of 3 travel lanes will be open during daytime hours (5 a.m.–10 p.m.) ROUTE 1 SOUTHBOUND: Approaching the Chelsea Curves from the North Shore, the work zone is in the median. All 3 travel lanes are open during the daytime hours (5 a.m.–10 p.m.)

Construction Update: Chelsea Curves Construction Look-Ahead Through Feb 20 – Chelsea Record

• Route 1 Southbound: Completion of new bridge deck and placement of Bridge Barrier will continue through the Chelsea Curves. For more information about the Tobin Bridge/Chelsea Curves Rehabilitation Project, please visit the project website: mass.gov/tobin-bridgechelsea-curves-rehabilitation-project.  Completed Work •All remaining work is within the Chelsea Viaduct portion of the job. Work has begun on the reconstruction of parking lots underneath the Chelsea Viaduct. Travel Tips Drivers should take care to pay attention to all signage and move carefully through the work zone. Police detail, lane markings, temporary barriers, traffic cones, signage, and other tools will be used to control traffic and create safe work zones.

Chelsea Curves Construction look-ahead through Jan 9 – Chelsea Record

This is a brief overview of construction operations and traffic impacts for the Tobin Bridge/Chelsea Curves Rehabilitation Project. ROUTE 1 TRAFFIC IMPACTS •ROUTE 1 NORTHBOUND: Approaching the Tobin Bridge from Boston, the work zone begins in the right lane. 2 of 3 travel lanes will be open during daytime hours (5 a.m.–10 p.m.). •From Monday, 1/4 through Friday, 1/8, Route 1 Northbound will be reduced to a single lane to set prefabricated bridge units (PBU’s) during the nighttime (9 p.m. – 5 a.m.). •ROUTE 1 SOUTHBOUND: Approaching the Chelsea Curves from the North Shore, the work zone is in the median. As of Wednesday, 12/23 all 3 travel lanes are open during the daytime hours (5 a.m.–10 p.m.).

© 2024 Vimarsana

vimarsana © 2020. All Rights Reserved.