Route 1 Southbound: Completion of new bridge deck and placement of Bridge Barrier will continue through the Chelsea Curves.
For more information about the Tobin Bridge/Chelsea Curves Rehabilitation Project, please visit the project website: mass.gov/tobin-bridgechelsea-curves-rehabilitation-project.
Completed Work
•All remaining work is within the Chelsea Viaduct portion of the job. Work has begun on the reconstruction of parking lots underneath the Chelsea Viaduct.
Travel Tips
Drivers should take care to pay attention to all signage and move carefully through the work zone. Police detail, lane markings, temporary barriers, traffic cones, signage, and other tools will be used to control traffic and create safe work zones.