Virtual capital tour continues
By Sheryl Roadcap - sroadcap@sidneydailynews.com
SIDNEY —The virtual capital tour of improvements in the city of Sidney continued Monday evening during the Sidney City Council workshop session.
The update on the city’s streets and water projects, the Shelby Public Transit and Sidney City Airport was given by Public Works Director Jon Crusey.
Shelby Public Transit will purchase two new buses for a total cost $130,044, and one new accessible van for a total cost $67,277.
Sidney City Airport will begin the construction of a parallel taxiway in 2021 and is expected to be completed in 2023. The earthwork cost for 2021 is $400,000; the drainage work in 2022 will cost $250,000; and the paving in 2023 will cost $850,000.