Are directly associated with m. E. P. And m. E. P. Installation and systems and commissioning which all have a string of dependencies on getting permanent power. If we were to remove the wrong assumption about where the water hookup is on the critical pact, would all of those shift back . Thats my initial reaction and the word that i get this week is, no. Because of again, state of readiness or state of completion with electrical rooms and main distribution rooms for the low voltage arent quite where they ought to be. And they are applying more resources. Theres 200 electricians out there, but, you know, without you know, without the appropriate pieces of equipment and the equipment being led up by the distribution of power and low voltage, systems commissioning is constrained. As well as to a certain degree exterior and enclosures and waterproof, not so much waterproof but exteriors and enclosures because theres some devices and what have you that are associated with that work as well. Exterior and enclosures i think are a little bit impacted by a hanger oner in terms of the of the modular booths that are yet to come to that. Its been a bit of a drag point as well in terms of the timing of the arrival for the prefabricated booths. I understand that come january well see the first booth which is running a little late as well. Rumor has it that since were kind of a oneoff, you know, with all of the hurricanes and what have you and when fema went looking for modular buildings those companies kind of paid more attention to the regular customers. So were pushed and strained on a number of fronts, but principally, again, about getting wires in place and equipment led up. And im im sure that i can confirm over the many years that nothing gets drivers more upset than not having bathrooms. And i mean finished bathrooms. I mean, they go really on that one. So make sure that those bathrooms are yeah and some of them are associated with those portables, so, for instance, the standup come december, weve got the bathrooms in place, a temporary trailer which has been described to mow as kind of the wedding trailer. So theyre hard you know, Running Water and the whole bit. So were paying attention to those needs. Moving through schedule a bit. I really dont have much to add. Were just tracking with the bus operations. Again, were excited to see the buses on the plaza as well as the deck. You know, i see the network and Access Control and all are going to show drag points as well if we dont get the low volt. Nothing really sea change here. With that i will ask martha to come up and to show you some of the retail readiness and the Facility Readiness and ill come back and speak to our risks. Good morning again. So theres not much new to report on this particular slide, the focus has been staying on track to accommodate amtrak and greyhound for them to move in just at the beginning of april. So everything is on track there. And ill discuss a little bit more in a little bit more detail, in the Facility Readiness report. The same is true here on the facility the Facility Maintenance. The r. F. P. Submissions are on target as noted. Ill talk a little bit more about that in the Facility Readiness report. The commissioning and training lines are completely dependent on web corps. And again with b. R. V. In the roof park they are on schedule, and the focus is the refinement of their programs and solidifying the calendar. More detail on the Facility Readiness report. And with the media they remain on target per their schedule. At this juncture they shift from planning and designing to creating and testing and, again, the timeline at the bottom goes past march because they continue to test and refine. And colliers and p. R. I. , im going to talk at length about the colliers schedule during the Facility Readiness report. P. R. I. Will be on target to have popups ready in march. Good morning. So a quick update on the facility security. The contract for the Security Guards and ambassadors and the Law Enforcement m. O. U. , were wrapping up negotiations for those and well be bringing those to the board in january. And the security s. O. P. S, the preopen and security training, we will have those complete by public opening of the building and the code of conduct, we will bring that to you early next year, thats progressing well. And the psim ec s mns are progressing. Is there a reason that the first two are slipping every month . Were still in negotiations with the m. O. U. Next month or do we really think that were very close, moments away, i would say, so, moments, days, were very close. Thank you. Thank you. I think that we would have to move to the general meeting, so by january 1st well have an agreement with them . Yeah. Were hoping to wrap things up this week, actually. Thank you, ill hand it back to ron now. Okay, that takes us to our one and only real risk slide that we have been carrying and its all about schedule. And, again, i cant overemphasize the need to progress to the electrical, normal and low voltage work. We are seeing progress. We have permanent power. Were progressing through, bringing the redundant power which, again, is an elective feature. P. U. C. Is wrestling a bit on bringing some wires to their volt so they can actually read their meters and bill us, but all in all, i think that bringing power to the facility is there. And i know that web corps has been enlisting a bit more and more in advancing the distribution and im looking to web corps to speak to that a little bit after this slide. And i have been tracking also the column covers and the e2 pylons and the e2 pylons, a collection of lowvoltage devices, that are scattered about the park and the good news is that theyre finally in production and i understand that the first batch of 15 are going to arrive the day after christmas on the 26th. So well start advancing that. Again, its impacting the park to a certain measure because theres a lot of leave outs waiting for the arrival of this electrical device. You know, it provides the lighting, the cameras, alarms, what have you, theyre all funneled through i think that theres 140 some odd pylons out on the park. So theres a bit of catchup there but the good news is that they are in production and they are going to be streaming over the next 10 weeks i think to get them onsite. And likewise, the column covers, i think that theyre starting to fill their pace and theyre starting to come together and get in place in better fashion than they had been. So theres a little bit of good news there. Again, underscoring that the bus plaza is a prime focus as well as the grand hall and the bus deck. And as you saw from the photos theres a lot of elements that have progressed, starting to take shape. But im concerned about how acutely constrained we are by some of the underperformance by fisc. And with that the next slide is the main bullet items of mitt aggression that we have been employing in the last number of months, with some success, but some modest modest success in some areas. And with that im asking that Jess Peterson with web core to come up and start elaborating on how we might adjust and tweak this mitigation to better better get us towards completion where we need to be. So, thanks, jess, for coming. I know that your schedule is constrained. Theres always something to do. Lots of work going on in the city. Good morning. And so i wish that it was easy and its just talking through some of the bullet points. Your question, ed, was around why did we slip a month in the last month . We have been told that permanent power and water would be received in november and we dont have it at this point in time and, yes, theres some concurrent issues going on with our electrician. We find i dont know well, maybe ill back up, so at the beginning of the year i realized that theres been more attention needed at the job. I probably spend at least once a week out there. And we typically bring in the principals of the company to be able to talk to many of the issues that are out there. And, certainly, fisc is one that we have been talking with regularly. Things are things are mixed and a little complicated and part of it has to do with just what it takes to get the buildings up and exercised once we do get power and water. We have 12, but we have three other vaults that we have both inspection and green tags and what we find, i think that it was yesterday afternoon or this morning, is that theres a dedicated sub 4p. U. C. That has advised us they need to get additional equipment before the transformers can be working. So its probably giving more detail than needed but theres unknowns that come up and things that do happen. And the team has the entire team t. J. P. A. , and turner and our group and our subs, have been working to keep mitigating those things time and time again. And were getting down to the end so its becoming much more known. And the physical work is going to get done and the physical you know, mechanical and electrical and plumbing will get in and a lot is getting it up and running and exercised. So hearing of that, were already thinking how we mitigate those kind of things so we have some extra temporary Power Service that well start to bring on with some of the permanent so when we do get water over the weekend that we can start turning on some of the equipment rooms. And start exercising some things, probably by the end of next week, if we do do that. But we do need to get both temporary, water, power and even some final permits. I think that one of the things that was certainly with some wisdom aboard here, in making a leadership change a year and a half ago was their ability to go in and see what is left to do and there were still systems not designed and still needed to be done. So that being recognized, we have been in the process of working with tjpa to design those systems and the Fire Department and theres some Communication Systems they need that we still dont have a permit for. So its hard to get done when you dont have water, power and permits, but the one thing that i can say is that the team, you know, has tried to stick to the original schedule as much as theres been the changes through the entire duringation of the job and its work duration of the job and its worked because theyre trying to be as collaborative as possible and anytime that something comes up to try to work around it. And, unfortunately, its a very complicated oneoff job and its not a hotel that we have done 10 times and we get to do again. And unique things do come up and the team is working heroically to do, that and 245eur staying active to get there and keeping their eye on it. So those are the kind of things that were really working to mitigate at this point in time. Can i just ask so with the current and the pr proposed mitigations and whatever the current expectations are with water and power and permits, what do you think what does that mean in terms of substantial completion . Can it come back into march . No. So weve lost march at this point . Yeah, i mean, we our original schedule showed 10 months after getting power wed have the building on and the team narrowed that down to just around five months, 4 1 2, five months earlier this year. And, you know, were continuing to window it but were getting to a window where there are a lot of electrical rooms and n. D. F. Rooms and rooms for distributing all of the data and we found out yesterday that the i. D. F. Rooms designed five years ago for 208 power now need 120 so now we have to go through a change and that was just found this week. So some are going to be easy to come up with and others are not and so if we can focus on getting that permanent power, its roombyroom, systembysystem that has to come up and has to be flushed and has to be commissioned and were at that edge of being able to do that. Theres not an acceleration path, unless somehow some of our subs stumble and fall and d dont get there and thats what were keeping our eye on. Supervisor reiskin can we have a completion date, whenever it is, april . When will we have power . Thats what were working with with both the team. We need to get the vaults finalized so we can get power into the building. We arent in a position to start turning anything on in sequence yet and we dont know when well be able to until we get the stepdown 480 power from the three vaults. Supervisor reiskin all right. This board has said that theres any assistance that any one of us can provide weve had 12 power into the two extension vaults, yes, but not able to bring it into the main switch. I dont want to hear he said she said can you speak into the mike . Were leaning together and trying to knock down the obstacles as they go and we definitely differ on kind of the driving forces as to when things were ready to be advanced, the permitting, versus when they were to be advanced to permitting and we can get this and it will be in the coming year and our focus right now is to lean in and make sure that we address the issues and the truth is that right now distribution, the state of completion of distribution of the utilities throughout the building is not where it should be. Whether or not theres water or not you need sinks and toilets in place to have an operational facility. You need racks populated and you need transformers tested and some of them are constrained and some of them are not and, again, i think that as said over the last last two years that we have been here we have all leaned in and been as collaborative as we can and pushed where we can and we meet every week and try to take down the big issues as much as we can with our project leadership team, and quite frankly, that agenda has been fairly light because its really just progressing the routine. And when big obstacles come were fairly adept at knocking them down. But i think that jes is right that theres a lot of work with commissioning and were just not there in terms of the state of completeness that we ought to be. And, you know, from my vantage point, the drag point is a lot of electrical and a lot of shop drawings that went back and forth with the fire marshal and theres a lot of minutia to tease out at the design level and the shop drawing level. And i think that weve arrived there with the fire alarm finally, but, you know, thats a known risk and a known issue that needed to be muscled through. I dont know what more to add but we are still trying very hard as a team to address these things, but clearly walking out there in tomorrows of lit up electrical rooms or low voltage, its not near where it needs to be. Anything i might add is that i mean, yes, our contract does finish on december 22nd, but what well try to do is to focus on the things that are needed by tjpa and, obviously, the muni bus was needed prior to that and even when we found out, you know, a couple months ago that it was needed in early december, the team rallied and they figured out what theyd do and how to corden it off and make sure that its safe for passengers and give them time to test. So we turned over a portion of the facility in early december, because it was needed. And so were going to keep looking at the kind of things that you need and well keep working as a team to figure those out. Were not worried at all what the contract says one way or the other and all we want to do is to try to solve the issues that arise and try to get you in as quick as possible. In your planning, when do you think that tjpa will get the keys to the facility . Say that again, please . In this teamwork or this progressive trying to meet strategic needs, when do you think that well be able to get the keys from you and to be able to meet the deadlines or the schedule that we have . So in getting the keys from me it means that everything is done absolutely 100 . Thats right. Right. And so because thats always nuanced theres a few punch list items that are usually not that big of a deal and the biggest thing that you really need is the commissioning done and ultimately the security up and running and i can see what would take place is us to try and find ways to hand off to you as they are needed even though you dont have the keys its your house and were still doing a few things but we still have some things well have things to finish certainly into april. So i guess that the question is, when will we get the master key that opens up all of the rooms in the building . Versus bits and pieces . Well, the easyiet way to get the master key is to go ahead and not give you anything, just let us finish the box and get done with it and then turn it over but we know that is not possible so in order to do muni we had to pull people from somewhere else and finish the phase and we needed that earlier but now it takes longer on the site work. To get the bus deck done we have to pull people off so i wish that it was an easy answer but by trying to mitigate and give you the things that you need as you need them is the way that its going to take longer to give you those master set of keys. I will just ask that we ramp up and we continue to just do everything that we can and this board has always said that anything that we can do to talk to some of these Utility Companies or to do that for other projects and we do have a commitment in get the station open as soon as possible. Thats really clear and i wish that it was as easy as ramping up and id say that its still more of the things that we find. Typically in the schedule youve gone ahead and worked, you know, five days a week and you have weekends to catch up when you find things or second shifts or whatever else and we have gobbled all of those thing and so when thing comes up and its our issue or a design issue or something, theres no more room to navigate. So those are the things that we hit the hardest to try to figure out and its just a matter of keeping the team focused on figuring out the solution to the issue, resolutions as quick as possible and getting it done. So were not afraid of whats ahead of us, we just dont know the unknowns that could come up. Thank you. Thanks for the update. The challenge that i have is, you know, ron has been great in giving us updates every month and its been very clear that the hes been very political in saying m. E. P. But its very clear to me that the e. Has been the one that has been behind. And so following up director reiskins concerns and the concerns of the board, what are you doing to prevent ron coming back next month and saying that it slipped again . What weve done is to bring in additional help. And not only augmenting but supplementing. For example, the air refuge and the Emergency Response system we got an understanding of what the Fire Department needs here at the end of november and we have about 5,000 lineal feet of conduit and were getting it done, and so theyre off now doing it. So were trying, as those thing comes up, were trying to bring in others to be able to handle some of the unique things that come up so we can keep our eye on doing the basic work and getting done. What are the consequences of coming back next month and ron saying that it slipped again . What are the consequences . Not meeting the dates that are being presented this morning . Yeah, there are unknowns in the industry. I mean, were working through what we know. So, i mean, id love to be able to say that i can turn the keys over to you but where we also need things too and we dont have everything, but its coming in time. Just with all due respect, this is not the first building that the work crew has built and we have three months to go, and how could there be so many unknowns when we have done this before before so many times . I mean, it seems to me that by this time with where were at we should have a clear path of what the obstacles we need to remove and what to expect. If we were three years back, i would understand, but were not. It seems that were arguing whether we have power or not and we say that we have power in august. I dont know when they submitted to the p. U. C. The application to when they wanted water or not, but i think that it was submitted late but ron worked and were getting water in monday. What else you were involved in the preconstruction for several years, since 2010, so you know the plans inside and out. Yeah and you also know that we were supposed to have all of our subcontractors in board until 2013, and we didnt get them all on board until 20152016 because of the significant changes made throughout time so an appropriate way to do it is to get there early and do lots of preplanning and wash through all of those issues and we didnt necessarily get that timeline. Im not sure and to close it, i think that we all get the point, i mean, we do need to work harder and we cant allow anything else to slip and things do come up as we get to the stage of the project and i think that the discussions are healthy but we need to get and figure out that we dont slip anymore. Yeah, were doing everything that we can can i just say one thing director nuru, i want to make sure that with all of this discussion that were planning on having buses coming in in june with bus operations and the bus drivers are eager to get in here and you will see them whether youre done or not, and i am serious. June 1st, we heard that here. June 1st. To be clear. Thank you. Okay, that somewhat concludes my presentation and i want to underscore that despite all of the tensions that were working collaboratively day in and day out and identifying where we can maneuver and its true, you know, as we get further down the space to maneuver it gets narrower. And the focus is really to get the state of completion on those m. E. P. Disciplines moving as fast and complete as possible and with that i think that were concluding. Thank you. Ron, thank you for the update and thanks to the team. I just want to make sure that i am understanding when we talk about june 1st for a. C. Transit, sfmta will be there ahead of that and looking through the popup and the first bus i mean we have the five fulton on december 26th, and something in march for meaningful operation and i wanted to see how that all gets tied together with the popup and with security and making sure that its all lining up at the same time. Because if i look at the charts theres some gaps and so, you know, i want to make sure that when muni starts running, at least the signage is up and the advertising may not be running at that time, but its just great to see all of this stuff laid out and i just want to make sure that there are no gaps as we call it a softd opening versus full operation. Yeah, no, i think that the intent is to make it as active as possible. You know, some of those streams of activity have different Different Things pushing them and different constraints that are independent and different than the construction. So theres kind of a natural progression that may leave gaps that we need to focus on and try to narrow up, but, again, kind of the sequence of events to stand up a popup and or leasing is a little different than, you know, pushing on the electrician to pull more wire. But weve got our eye on both of those to advance. The key is, i guess, while theres different pushes and pulls on security and signage and advertising and construction, is to not forget that managing the Customer Experience when they get off the bus or get on the bus at the new center. First and foremost. And managing, you know, getting off and where to go and that is part of the Customer Experience, to make sure is that we manage those expectations or celebrate those expectations and experiences. Absolutely. Thank you. Clerk next item, 11, the Facility Readiness update. So today im going to review the lincoln Facility Maintenance progress and the status of the work as related to the park and the status of pearl digital medias work and the status of colliers leasing efforts that supplement what was already discussed. Status of the popup preparations. And update on transit readiness as related to the moving parts on the various agreements and then sydney will review securi security. As mentioned earlier, the focus has been getting ready for greyhound and amtrak. The primary focus of this discussion is the construction on the second floor. At this point the construction documents are complete and ready for permit submission and were doing this in parallel, the document review will happen with greyhound and amtrak next week in separate meetings. Primary update on the lincoln Facility Maintenance slide is that three proposals have been received from Marketing Services that lincoln needs to review for our recommendation to the tjpa. Key aspects of the needed services are creating a brand with an understanding of how to use the sales force naming rights agreement and the tjpa brand. Development of a site website that serves as a point of entry for colliers, pearl and p. R. I. And then also outreach in particular social media to generate and maintain customer traffic to the Transit Center. This slide represents a contract awarded within this last month to landmark industries. Its the waste and recycling services. Its an important contract in place. The timing was sensitive because equipment has a long lead team of anywhere from three to six months. With regard to costs, these are unit prices, services will be calibrated depending on the need. Note that there was only one respondent that was viable. However, pearl link and landmark prices are consistent with the market for large complex multitenant facilities with the mandated zero waste ordinance goal. And this slide is blank as a placeholder for facilities contracts and you will start to see those come in in the january and february time frame. With the daily operations of running the site, at this point, three of the five key Service Contracts are in place and thats cleaning and engineering and maintenance and sanitation and waste. Two that are in the pipeline that are critical to daily site operations are the computerized Maintenance Management system, support vendor. This contract is expected to be completed in midjanuary. And another key contract is the vendor that will support management of the technological backbone of the center. And that will also include a 24 will be 7 help desk for Service Problems and in terms of supporting the retail tenant improvement activity, the needed contracts are in place and these are the architect and the general contractor and then an attorney for Legal Support on the lease negotiations. So lincoln continues to work through its list of needed services for r. F. P. S to be issued by the end of this calendar year and the strategy is to get all of the r. F. P. S out and then spend january reviewing the responses that will then lead to selection, negotiation and contract completion. For the contracts to all be in place by the end of march. And this approach will enable review with Small Business outreach in mind. So some specifics to add to what is noted on the slide, discussions are underwa underwat a ministreet food market for some revenuebased activity. They are working with nois pop to have a concert series. Midjanuary is targeted is the targeted timeframe to have a draft Event Planning guide and an event proposal outline, and film photo shoot application in place. B. R. V. Is also developing a cohesive Fitness Program to package as an attractive sponsorship opportunity. Pearl is going to be here in february to present to the tjpa board their entire program. At this point theres three areas to highlight and the transit screen work with the operators is nearly complete and testing is scheduled to begin in january. And reconciliation with web core is in progress. The Media Players are the equipment that run the screens. I mentioned it here because theyre a critical piece of equipment for everything to be working. There are some 200 transit screens throughout the center. And pearl is actively out in the market reaching out to major brands for presence in the Transit Center. Can i okay. Sorry, i thought that i missed a slide. With colliers, already discussed is the activity in the pipeline and most of my update will be given on the next slide. On this slide the highlight is that the leasing signs will go up this week and the rendering that you see at the top right of the slide is what its going to look like. There are various locations that will be on the construction census and theyll move around as the census as as the fences come down. And the signs are metal and theyre 4 feet high by 8 feet wide and they again look like the image noted on the slide. With p. R. I. , they owe the final plan to include the bus plaza and specifically with the bus plaza, there is a coffee vendor that is interested. However, he wants to see what it will look like once its open. And to stand and observe the traffic. And then we also need to make sure that theres a power source. If all of that falls into place putting up the Coffee Service will happen pretty quickly. And this is the slide on the schedule. So this last month colliers revisited the occupancy timeline and provided the tjpa with the update that you see today. The previous plan had the dots arranged as starting in q4 of 2018. These dots start in 22 of 2019. If you recall last month i outlined the various phases of how colliers has moved through its work. First phase was to develop, the second phase was to prepare, and the third phase i called blast to the market and the fourth phase is tenants. So we are currently in phase three, blast to the market. In general preparing for blast to the market took longer than anticipated, thus, contributing to the timeline shift. Some examples are the architectural contract. It was heavily negotiated where maybe the anticipated timeframe to negotiate was two months and it actually took about four. And another example is the lease template, making sure that all of the public requirements were incorporated into it, the original thinking is that it would take about a month and it took two. And the website had to be redone at the point, the naming rights agreement went into effect and that added to the timing. The website is particularly important because it contains all of the needed information that a prospective tenant needs in order to make an natural decision, including the line drawings of each space and these are prepared by the architect. And it is important to note that colliers was aware of pentup interest in the Transit Center based on the informational tours that happened throughout the summer. So being prepared to address the expected rush of inquiries was necessary in order to be able to efficiently new through a deal to completion to create a good First Impression and to create confidence. As such the revised timeline is a reflection of where we are today, taking into consideration the timing of the formal reach out to the market and the steps that it takes to work through a deal, some of which was outlined earlier. According to colliers, leaseup time can be anywhere from nine to 18 months, depending on the complexity of the deal. And build out of the space. And so backing out from backing up one year from 22 of 2019 takes us to q2 of 2018. And so that anticipates much leasing activity over the next few months. This slide is the transit Facility Readiness. The focus of my update today are all of the moving parts associated with the various agreements to occupy the Transit Center. At this point the kog in the wheel is the agreement for the bus deck between a. C. Transit and the operators. In conversation this week her target for the bus deck between a. C. Transit and the Bus Operators is the january 24th, a. C. Transit Board Meeting. This week lois and i worked on looking at the consistency of the terms and conditions across the various agreements. This in turn impacts the sfmta agreement with the tjpa for occupancy of the bus plaza and this agreement will be completed this month and we just have a couple points to iron out. However, sfmta has expressed they will not take this agreement to their board until the agreement with a. C. Transit is also completed. So agreements are approval at the february sfmta Board Meeting. As such the bus plaza agreement would not be presented for board approval until march. I hope thats not too confusing. Its confusing to me. You got this look on your face. Why is it that sfmta and the bus plaza has anything to do with the bus deck, because its which buses go up or down . So the information thats been conveyed to me is they want to tie it up into one package. Oh, okay, well, theres no reason for that, but thats what they want to do. Thats what im working with. Oh, okay. Yeah, because theres no no other connection than that political connection. Is that agreement coming to this board in march impact anything in terms of startup timeline . No, it doesnt, because as you have heard from the earlier conversations, operationally at least on the facilitys readiness side, well be ready to go. At that point its really related to the presentations that you heard earlier on the construction. But i guess that the risk is not m. T. A. Or a. C. Transit and the risk is that we have other operators, amtrak and greyhound and they need to enter into agreements with a. C. Transit to operate on the bus deck. Greyhound also has an agreement, separately with amtrak and greyhound to use the office space on the second level. Right. And greyhound entered into an agreement with us pending their agreement with a. C. Transit so were working on them with improvements and so forth and amtrak asked that they refused to enter into an agreement with us until theyre finished their agreement with a. C. Transit. So thats so, yeah, thats my last point was that now that the agreement between a. M. Track and the tjpa for the occupancy of the second floor is stalled all together. They are reticent to move forward until they have a full understanding of the Financial Impact of the agreement between a. C. Transit and amtrak coupled with the Financial Impact of the second floor lease. We have been having backandforth conversations with amtrak since august and last friday i talked with the senior director of real estate and he made clear that theres not going to be any movement until they understood the financial piece, the full picture, again, because they want to present the full picture to their board. However, i dont know at this point when when amtraks board when amtraks board meets. As i noted earlier we have moved ahead with the planning for the construction because we cant we cant impact the greyhound occupancy of the second floor. What i dont know and ill check this out with our attorneys and i dont want our attorneys to be holding this thing up. I dont know why it is that draft that wed have to come out of a. C. Transit on a Board Meeting with the full board approved draft because these things are going to be changed as they go. So im going to find out if we cant come out earlier and say, well, this hasnt been approved by our board because thats probably our next Board Meeting is about then. So, i mean, i dont want that problem to just be in there and lets get some drafts going around and get some, you know, early input from everybody. Well, there was the initial excuse me so there was an initial draft distributed a couple weeks ago and so thats where it is now. Okay. Its in the draft process so all of these other agencies do have this draft they do have the initial draft. Lois and i talked about, again, making some modifications for consistency because theres so many agreements, just to make sure that that some of the language is the same so that theres not theres not a misunderstanding or a lack of clarity. Okay, good, because you know how many changes a board makes to a draft zero. So lets get working on it. I think that the focus is really on amtrak because the rest of them are all in the family and work things out. But amtrak is the one that we need to figure out so that they can yes, we need to figure out what to do with amtrak. Theyre further behind than everyone else. Yes, thats often the case. Okay. As our new member can tell you. Good morning, again. So Facility Readiness and security, were completing the negotiations with the contractor that was selected through the Security Guard r. F. P. Process. Well have select especially trained Security Guards that will fill the ambassador positions and the m. O. U. With Law Enforcement, we are anticipating completing the m. O. U. Within the next couple days and well bring there to the board in january along with the Security Guard contract. The negotiations have been more complex than we expected and as we said the schedule has slipped a month on that. And the Transit Center code of conduct is under development and we anticipate to bring that before the board early next year. Okay. Any board member questions . Thank you. Thank you. So i have questions back on the retail. So we were supposed to be up and running this month, right . We now have a partial start this month as director gee said and the schedule is showing the sfmta full service in april may timeline as we have talked about. A. C. Transit, june 1st. And now what im understanding from this chart is that it would be a full year later before wed have any retail besides popup, in the Transit Center . So for a year after the sixmonth delayed startup theres just going to be construction site and the retail zones of the Transit Center . And thats six months worse than we thought a month ago . Well, i dont know if i would yes, its between three between three and six months. I heard some of the explanation just hard to understand i mean, its bad enough on the Construction Side that we lost a month in the last month and we have lost six months with regard to retail. I think that you heard the explanation but i think that really the original proposal, schedule, that were presented to you was probably not realistic given with what we know right now. And we thought that wed have full retail in the Fourth Quarter the Fourth Quarter of 2018. And given the process of getting tenants finding out from tenants what improvements they need to do construction and given that process its not realistic, probably, to i dont know you know, based on all of the discussions that we had, i dont know what schedules we can have any confidence in at the the moment. What i would say as a mitigation with regard to what the facility looks and feels like on the inside, i think that well have to expend more effort on making it not feel like youre walking through a Construction Zone and its going to need more temporary treatments and signage and other things to mask all of the unfinished portions of this building starting as we talked about from the bus plaza in two weeks to other parts of the building starting this spring and summer. If the retail is not going to be there, its not going to be there, but we dont want peoples experience for a year to be negative as they go through this 2 billion facility. It also will require i think perhaps more and extended popup or other activation so it doesnt feel that people are walking through a hollow construction site masked by signage. That would have been the case regardless because the retail construction will be going on and so, yes, that is the longer the duration and the greater the need to make that feel like a welcoming environment. And, again, the d. R. V. Will have the part activated with programs and activities and, yes, the popups will be in place. Mr. Chair. If i may all things being equal, to a comment that was made earlier about the accelerated interest in the space and the numbers of potential entities that want to lease that space in recent weeks, theres nothing that procludes us from pussing them in place and making them operational. So when you say three to six months, we have folks who want to put their system in place and get operational, theres nothing from the building side that will limit our ability to allow them to come in . Thats correct. The pace of the deal is often driven by the tenant, the prospective tenant themselves. The time it takes for them to make a decision, and financial considerations, and the negotiation, that can take some time. And, again, it depends on the the sophisticated i will say tablecloth restaurant tour will take longer, for example, for the rooftop restaurant than, say, a smaller a smaller retail on the ground floor. Yeah so thats what is going to dictate i want to make sure that we dont have a number of willing participants with nowhere to go. Just to add to this, the assumptions that we have here is that the tenants, once they want to start tenant improvements they will have full access to their space to do their work and assuming that water and electricity is there for them to do it. If that changes, then this schedule may be impacted. With the assumption right now is that once we get them on board and they want to start tenant improvements they can do it and they would provide the space and give them what they need to do the tenant improvements within their spaces. Okay, thank you. Answer your question . Yes. Just to followup, i think that director reiskin said it and i want to be sure as we look at these schedules and do the technical stuff that we dont forget the Customer Experience for the transit riders as well as the neighborhood experience. I think that the neighborhood has been expecting things for a very long time and to hear that the schedule has slipped some more months is not probably going to go very well. And so we encourage to you work with the c. A. C. , to make sure that the expectations of the neighborhoods are managed and when the construction signs and everything comes down i think that there will be a big celebration but theyll keep waiting longer and longer and theres going to be some anxiety that needs to be managed. Yep. Im so glad to hear this and this has been a huge transit concern for a long time that when this opens the facility has got to be welcoming and people have to be comfortable in it because we really want to increase the ridership in a hurry to it. Absolutely. Really important. Okay, thank you. Clerk a transfer from program in the reserve of 25 million to a new line item for base building improvement and tenant improvement allowances in the Phase One Program budget. I talked about this, if you have any questions, director sara debord can answer. I move approval. Second. Clerk with no items to comment on the item, director harper, director kim, director reiskin, and director sartipi. And director tripousis. And thats six ayes and item 12 is approved. Item 13 is authorizing the executive director to write a venture agreement with the San FranciscoMunicipal Transit Agency to have certain bus operations in a portion of the bus plaza on an interim basis. I would like to recuse myself from this one. I dont know if that needs a motion. I can answer any questions on this. I think that this is important to get the buses rolling through here so on that one id like to make a motion to approve. Clerk first and second and no members of the public to comment on the item and director reiskin is recusing himself, [reading of names] thats five ayes and item 13 is approved. And call your next 14. Approving amendment number 4 to the intergovernmental agreement, number 2 related to the construction of the Mission Street bus supporting island and the extension and an aggregate not to exceed cost of 1,081,000 and not to extend to the amount for all services under agreement 2 and to extend to december 10, 2019, and the members of public to comment on the item. And director reiskin recusing himself. Moving approval. Second. Clerk [reading names of directors] thats five ayes and item 14 is approved. That concludes your business for today. It concludes our meeting, so, thank you, everyone. Ok, lets get started. Welcome to our special, special, special budget and finance Committee Meeting for monday, december 11th, 2017. I am norman yee and i will chair this committee as soon as everyone is quiet. Thank you, very much. I am joined by supervisor jeff sheehy