Despite wet weather raising water levels in the Little Muskingum River this week, construction continues at the Cornerville bridge on County Road 20 in Marietta Township. (Photo by Janelle Patterson)
Warmer temperatures mean it’s construction season in Ohio, but the rains also equal some delays.
This was the story at the Cornerville Bridge in Marietta Township this week, with a pivot from drilling piers to abutment work.
“We kept working, but rain obviously slows down production,” said Washington County Engineer Roger Wright. “Unfortunately the spring floods got us this week a little bit.”
With a pier underwater of the Little Muskingum River after rains throughout the middle of the week, Wright explained, drilling had to pause.