Apr 9, 2021
The following construction projects are anticipated to affect highways in Washington and surrounding counties in the coming weeks.
All outlined work is weather permitting.
¯ I-77 resurfacing: A resurfacing project begins on April 19 on I-77 between Exits 1 and 6.
The project also includes guardrail replacement, drainage correction and concrete barrier upgrades.
The passing lanes of I-77 north and south will be closed.
Estimated completion: June 4.
¯ I-77 resurfacing: A resurfacing and concrete joint repair project is also taking place on I-77, between Exits 6 and 16.
The passing lane of I-77 north is closed.
Estimated completion: Aug. 1.
¯ City of Marietta signal/fiber optic upgrades: A traffic signal and fiber optic system project is taking place at various intersections in Marietta, including Putnam, Front, Third, Seventh, Greene, Pike and Acme Streets.