th Ave. to the South Dakota state line).
Description of Work: Pavement Repair, Curb and Gutter Repair, and ADA Curb Ramp Upgrades
Work in Progress: D&G Concrete Construction of Sioux Falls, the prime contractor for this project, has completed concrete repair from the South Dakota state line to Lawler Street. The contractor is currently working on concrete pavement repair from Industrial Road to Bridge Street. ADA ramp work continues at Bridge Street, Wicker Street, Howard Street, Blair Street and Milwaukee Street.
Traffic Alerts:
Lane closures are in place on Highway 18 from Industrial Road to Bridge Street with the westbound inside and outside lanes closed. Westbound traffic is diverted to the center turn lane.