NASA EGS, Jacobs preparing SLS Core Stage for Artemis 1 stacking


NASA EGS, Jacobs preparing SLS Core Stage for Artemis 1 stacking
May 6, 2021
The Core Stage of NASA’s first Space Launch System (SLS) vehicle arrived at the Kennedy Space Center (KSC) and was moved into the Vehicle Assembly Building (VAB) on April 29. The stage is now in the hands of KSC’s Exploration Ground System (EGS) program and prime test operations and support contractor (TOSC) Jacobs.
The long-awaited milestone allows EGS and Jacobs to work towards putting the whole Orion/SLS vehicle together and beginning months of testing to get it ready for the launch of Artemis 1. The stage is now in the low bay of the VAB, where some “traveled” work from the recently-completed Green Run design verification campaign will be performed in parallel with preparations for stacking with the new launch vehicle’s Solid Rocket Boosters (SRB), which are already in place on the Mobile Launcher in VAB High Bay 3. ....

United States , Aerojet Rocketdyne , Andrew Shroble , Michael Alldredge , Nathalie Quintero , Kim Shiflett , Philip Sloss , Glenn Benson Cory Huston , Exploration Systems Development , Stennis Space Center , Kennedy Space Center , Operations Aerospace , Vehicle Assembly Building , Stennis Space Center To Kennedy , Space Shuttle Program , Shuttle Program , Core Stage , Space Launch System , Ground System , Green Run , Solid Rocket Boosters , Mobile Launcher , Element Acceptance Review , High Bay , Integrated Operations Flow Manager , Integrated Modal Test ,

Ten month schedule to ready SLS for Artemis 1 launch after Core Stage arrives at KSC


Ten month schedule to ready SLS for Artemis 1 launch after Core Stage arrives at KSC
May 3, 2021
NASA’s Exploration Ground Systems (EGS) program is looking at a wide range of forecasts for when they can complete testing necessary to be ready to launch Artemis 1. The Core Stage of NASA’s first Space Launch System (SLS) vehicle arrived at the Kennedy Space Center and was moved into the Vehicle Assembly Building (VAB) on April 29 to prep for stacking with the new launch vehicle’s Solid Rocket Boosters, which are already in place on the Mobile Launcher in High Bay 3.
Approximately six months of work is anticipated to finish assembly and complete a long series of tests and checkouts of SLS and the Orion spacecraft it will send to the Moon, but current forecasts of this first-time integration work estimate closer to ten months to complete the necessary operations. After the vehicle is put together, weeks and weeks of testing to make sure SLS and Orion are properly talk ....

Launch Complex , United States , Cliff Lanham , Andrew Shroble , Michael Alldredge , Nathalie Quintero , Philip Sloss , Exploration Systems Development , Tail Service Mast Umbilicals , Stennis Space Center , Operations Aerospace , Kennedy Space Center , Vehicle Assembly Building , United Launch Alliance , Ground Systems , Core Stage , Space Launch System , Solid Rocket Boosters , Mobile Launcher , High Bay , Vehicle Operations , Shuttle Main Engines , Integrated Testing , Wet Dress , Multi Payload Processing Facility , Core Stage Green Run Hot Fire ,

NASA, Boeing looking to begin SLS Exploration Upper Stage manufacturing in 2021


NASA, Boeing looking to begin SLS Exploration Upper Stage manufacturing in 2021
March 4, 2021
Manufacturing and assembly development work for the Space Launch System (SLS) Exploration Upper Stage (EUS) is starting to ramp up at the Michoud Assembly Facility (MAF) in New Orleans. NASA’s SLS Program and EUS prime contractor Boeing are preparing to begin construction of the test and flight articles that will be needed to certify and fly the new upper stage’s first launch.
A structural test article (STA) will be assembled at MAF and tested at the Marshall Space Flight Center (MSFC) in Huntsville, Alabama. The first flight article will then be completed and travel from Michoud to the relatively nearby Stennis Space Center in southern Mississippi for a Green Run test campaign similar to the one that the first Core Stage is going through. ....

United States , West Palm Beach , Aerojet Rocketdyne , Steven Wofford , Dan Mitchell , Michael Democker , Philip Sloss , Todd Holloway , B Exploration Upper Stage Development Office , Development Office , Marshall Space Flight Center , Stennis Space Center , B Test Stand At Stennis Space Center , Michoud Assembly Facility , Weld Center , United Launch Alliance , Space Launch System , Exploration Upper Stage , Green Run , Core Stage , Critical Design Review , Exploration Upper , Exploration Upper Stage Development Office , Test Stand , Photo Caption , Vertical Weld Center ,