Strike Energy has provided an update on the West Erregulla Appraisal Campaign on behalf of the EP469 Joint Venture. Strike has completed drilling the ~2,050m long intermediate section of WE5 down to 3,635m and declared section depth within the Kockatea Shale.
Strike Energy has provided an update on the West Erregulla Appraisal Campaign on behalf of the EP469 Joint Venture. WE4 flow testing continues with the well continuing to clean up and favourable pressures measured.
Australia: Strike Energy announces West Erregulla update
10 May 2021
WE5 has commenced drilling operations and has completed drilling the first hole section down to a depth of ~ 1,567m MD.
WE4 flow test has commenced.
Strike Energy has provided an update on the
West Erregulla Appraisal
EP469
Current Operations
Rig maintenance and moving operations went smoothly, without incident and the rig has since officially spud WE5 at 12:00pm Saturday 8th May 2021. Drilling operations have subsequently commenced and the well has reached final depth of the first hole section at approximately a measured depth of ~1,567m.
At WE4, Strike has perforated 75m of the Kingia Sandstone and is commencing flow back followed by the production testing of the well.
Strike Energy announces West Erregulla update
25 Jan 2021
WE3 was successfully suspended after encountering an over-pressured gas column.
Strike Energy has provided an update on the
West Erregulla Appraisal Campaign well on behalf of the
EP469 Joint Venture.
Current Operations
Since the last update, Strike has successfully suspended WE3 with a series of cement plugs. Subsurface, Engineering and Procurement works are ongoing with regards to the plan on taking WE3 to final depth. Post the suspension of WE3, Rig 970 packed down, moved and setup at the WE4 lease. The operations went smoothly without incident and the efficient move has allowed for several maintenance programs to be carried out.