ECRL Terowong Dungun breaks through six months ahead of schedule, says Malaysia Rail Link chairman | Malaysia


Wednesday, 02 Jun 2021 05:09 PM MYT
MRL said the tunnel excavation works for Terowong Dungun had progressed to 97.4 per cent prior to the breakthrough, while its permanent lining had rose to a decent length of 702 metres. ― Picture by Hari Anggara
Follow us on Instagram and subscribe to our Telegram channel for the latest updates.
KUALA LUMPUR, June 2 The East Coast Rail Link (ECRL) project has recorded another major milestone as it achieved a tunnel breakthrough at the 871 metres single-bore Terowong Dungun in Terengganu six months ahead of schedule.
Malaysia Rail Link Sdn Bhd (MRL) chairman Tan Sri Mohd Zuki Ali said the overall infrastructure works for the tunnel was expected to be completed by the second quarter of 2022, months ahead of schedule barring any unforeseen circumstances. ....

Kuala Lumpur , Kuala Dungun , Peninsular Malaysia , Malaysia General , Sdn Bhd , Kota Baru , Terowong Dungun , Hari Anggara , China Communications Construction , East Coast Rail Link , Rail Link Sdn Bhd , Tan Sri Mohd Zuki Ali , Finance Incorporated , East Coast , Klang Valley , Malaysia Rail Link Sdn Bhd , East Coast Rail Link Ecrl , Mohd Zuki Ali , Covid 19 , Terowong Dungun , குவாலா லம்பூர் , தீபகற்பம் மலேசியா , மலேசியா ஜநரல் , ஸ்டன் ப்ட் , கோட்டா பாரு , சீனா தகவல்தொடர்புகள் கட்டுமானம் ,