The construction of the bridge began in 2014 after chief minister Nitish Kumar laid its foundation on February 23, and it was expected to be completed in 2019 | Latest News India
The Patna High Court Wednesday criticised Bihar government and contractor SP Singla Construction for the collapse of part of the four-lane Sultanganj-Aguwani bridge, which is being built over River Ganga in Bhagalpur district
Bihar bridge collapse: The company, SP Singla Construction, has been asked to explain why it should not be blacklisted by the government and penalised further.
According to its website, the construction company got the contract from the Municipal Corporation of Greater Mumbai. The project is aimed at reducing the distance between Goregaon and Navi Mumbai from 75 minutes to around 40 minutes