Published May 26, 2021, 8:49 AM
CEBU CITY The Cebu-Cordova Link Expressway (CCLEX) is already 70.33 percent complete.
As of April 2021, the Cebu-Cordova Link Expressway Corp. (CCLEC), reported that the overall Engineering, Procurement, and Construction (EPC) progress of the 8.5-kilometer CCLEX is at 74.86 percent.
With the progress, CCLEX is seen to be substantially completed by the end of 2021 and to open to motorists in the first quarter of 2022.
ALMOST COMPLETE. The picturesque Cebu-Cordova Link Expressway (CCLEX) is already 70% complete and is expected to be operational early 2022. (Photo courtesy of CCLEC)
In its project updates, CCLEC reported construction milestone with the completion of the casting of all 446 Nebraska University (NU) girders required for the entire stretch of CCLEX.