Trial of power project unit a success: NLCIL


Updated:
February 04, 2021 23:32 IST
500 MW capacity lignite-fired boilers of the NNTPP are the first of its kind in India
Share Article
AAA
500 MW capacity lignite-fired boilers of the NNTPP are the first of its kind in India
NLC India Ltd. (NLCIL) on Thursday announced that it had successfully completed a 72 hour continuous trial operation of the 500 MW second unit of the 2 x 500 MW pit head lignite-fired Neyveli New Thermal Power Project (NNTPP) at its rated capacity on Wednesday.
According to a NLCIL official, the 500 MW capacity lignite-fired boilers of the NNTPP are the first of its kind in India. “The first unit was already commissioned and the power plant will be fully operational,” he said. ....