Province will complete Site C dam with new $16 billion price tag


But cancelling the project now would be an even worse deal for taxpayers, the government concludes.
Cancelling Site C when it was half done would have meant laying off 4,500 workers, just as we re coming out of the impact of the pandemic, Premier John Horgan said in a press conference Friday. It would have left us with a $10 billion debt and nothing to show for it.
That $10 billion debt would have meant a rapid increase in rates for people on average about $216 a year starting right away, and that was also something we were not prepared to do.
He added that the project was one that his government would never have started in the first place, but also noted that some of the cost overruns the project now faces are ones that no one could have anticipated. ....

Muskrat Falls , Peace River , Peter Milburn , Ken Peterson , Christy Clark , John Horgan , Bruce Ralson , Doug Allen , Kaare Hoeg , Bc Hydro , Bc Utilities Commission , John France , Low Carbon Innovation , மூஸ்கிரத் விழும் , சமாதானம் நதி , பீட்டர் மில்பர்ன் , கேன் பீட்டர்சன் , கிறிஸ்டி கிளார்க் , ஜான் ஹொர்கன் , காயங்கள் ரால்சன் , டக் ஆலன் , பி.சி. ஹைட்ரோ , பி.சி. பயன்பாடுகள் தரகு , ஜான் பிரான்ஸ் , குறைந்த கார்பன் கண்டுபிடிப்பு ,

Site C dam project will proceed


The project on the Peace River near Fort St. John was started by Christy Clark’s B.C. Liberal government in 2015. However, Milobar called the latest cost overruns “disappointing.”
On Friday, the province announced the project’s price tag had ballooned to $16 billion, about $5 billion more than the last estimate. Milobar said during the transition of power between the B.C. Liberals and BC NDP in 2017, the New Democrats confirmed the project was on time and on budget. 
“To see it now, essentially double in costs and well behind schedule, is concerning,” Milobar said, adding he hopes the latest project team restructuring and experts will bring an end to cost overruns and project delays. ....

United Kingdom , Peace River , Peter Milburn , Peter Milobar , John Horgan , Kamloops North Thompson , Christy Clark , Ken Peterson , Doug Allen , Kaare Hoeg , Insurance Corporation Of British Columbia , Bc Hydro , Bc Ferries , Bc Safety Authority , New Democrats , British Columbians , Milburn Review , Project Assurance Board , John France , Insurance Corporation , Wilderness Commitee , ஒன்றுபட்டது கிஂக்டம் , சமாதானம் நதி , பீட்டர் மில்பர்ன் , ஜான் ஹொர்கன் , கம்லூப்ஸ் வடக்கு தாம்சன் ,

Site C construction continues for $16 billion, one-year delay


Site C construction. (BC Hydro)
VICTORIA, B.C – The Government of British Columbia announced it’s continuing with the Site C dam project for an estimated $16 billion with a one-year delay.
The decision comes after a report done by Special Advisor Peter Milburn and independent experts deemed Site C as safe. Milburn’s report states improvements are needed to enhance project oversight and risk and commercial management.
Milburn, who was appointed to conduct the report in July 2020, is a former B.C. government bureaucrat with a background in civil engineering. Last month, the province announced that two international experts would be evaluating the site for safety issues. ....

Ken Peterson , John Horgan , Doug Allen , Brtish Columbians , Kaare Hoeg , Northern Health Authority , Bc Hydro , Canadian Dam Association , British Columbians , Premier John , Project Assurance , John France , Technical Advisory Board , கேன் பீட்டர்சன் , ஜான் ஹொர்கன் , டக் ஆலன் , வடக்கு ஆரோக்கியம் அதிகாரம் , பி.சி. ஹைட்ரோ , கனடியன் அணை சங்கம் , ப்ரிமியர் ஜான் , ப்ராஜெக்ட் உறுதி , ஜான் பிரான்ஸ் ,