NIA: Implementation of P11.2-B Jalaur Project on track


ILOILO CITY, April 30 (PIA) – The National Irrigation Administration (NIA) said that the implementation of the P11.2-billion Jalaur River Multi-Purpose Project Stage II (JRMP II) is still ahead of its target.
In a virtual press conference held April 29, Engr. Jonel Borres, acting project manager of the Project Management Office (PMO) of JRMP II , said that the implementation of Iloilo’s biggest irrigation development project continues to gain momentum.
“We are hopeful that we can finish the project by the year 2023,” Borres said.
The over-all physical accomplishment of JRMP II, considering both Government of the Philippines (GOP) and Loan Proceed (LP) components, is recorded at 37.83 percent, as of first quarter of 2021. ....

Iloilo City , Jalaur River , The Philippines , Steve Cordero , Jonel Borres , National Irrigation Administration , Management Office , Jalaur River Multi Purpose Project Stage , Project Management Office , Loan Proceed , Jalaur High Dam , Jalaur High , High Dam , Afterbay Dam , இளோய்ளோ நகரம் , தி பிலிப்பைன்ஸ் , ஸ்டீவ் கார்டேரா , மேலாண்மை அலுவலகம் , ப்ராஜெக்ட் மேலாண்மை அலுவலகம் , உயர் அணை ,

Construction of P11.2-B Jalaur River project exceeds works target


ILOILO CITY, April 21 (PIA) – The implementation of Iloilo’s biggest irrigation development project Jalaur River Multi-Purpose Project Stage II (JRMP II) continues to gain momentum and is ahead of its target.
A press report from the JRMP II Public Relations Team, citing the Project Management Office, said that for the first quarter of 2021, the over-all physical accomplishment of JRMP II, considering both Government of the Philippines (GOP) and Loan Proceed (LP) components, is recorded at 37.83 percent.
According to the report, this is 6.11 percent more than its target for the same quarter which is 31.72 percent.
This P11.2-billion project development, said the report, supports the battle cry of the National Irrigation Administration (NIA) – as chief implementing agency, for a continued implementation of essential irrigation development projects and programs amidst the pandemic with the official tagline #TuloyAngDaloyNIA. ....

Iloilo City , Jalaur River , South Korea , Alibunan River , The Philippines , Stevee Cordero , Jrmp Ii Public Relations Team , Economic Development Cooperation Fund , National Irrigation Administration , Management Office , Jalaur River Multi Purpose Project Stage , Relations Team , Project Management Office , Loan Proceed , Jalaur High Dam , Jalaur High , High Dam , Afterbay Dam , Alibunan River Catch Dam , Highline Canal , இளோய்ளோ நகரம் , தெற்கு கொரியா , தி பிலிப்பைன்ஸ் , பொருளாதார வளர்ச்சி ஒத்துழைப்பு நிதி , மேலாண்மை அலுவலகம் , உறவுகள் அணி ,