Upper Tamakoshi in final state, tunnel ready by April 21 »


(Image for Representation)
Major works as intake, tunnel, transmission line and substation have been completed.
There are now minor civil and mechanical works going on under the project.
Although one of the national pride projects was expected to be completed before coming to New Year (2078BS), it was delayed because of Covid-19 and some technical glitches.
Lot-2 Hydro-mechanical contractor company has committed that the works as wielding and painting would be completed by April 21.
Similarly, the installation of a penstock pipe has been over. Embankment/intake, main tunnel, powerhouse, tailrace tunnel as part of the major construction have also been completed. ....

Nepal Electricity Authority , Chairperson Of Upper Tamakoshi Hydropower Ltd , Upper Tamakoshi Hydropower Project , New Year , Upper Tamakoshi Hydropower Ltd , Hitendra Dev Shakya , நேபால் மின்சாரம் அதிகாரம் , புதியது ஆண்டு , ஹிதென்திற தேவ் ஷக்கிய ,