Norway: Equinor announces revised start-up date for Hammerfest LNG

Equinor has announced that, due to continuing consequences from Covid-19 and operational restrictions, the time of start-up of the Hammerfest LNG plant is pushed from 31 March 2022 to 17 May 2022. ....

Haug Equinor , Greteb Haaland , E Ampp News , Il And Gas Exploration , Xploration And Production , Nergy Pedia , Eological And Geophysical , Lternative Energy , Eavy Oil , Il And Gas Condensate , Icence Round , Il And Gas Ministry , Oil Companies ,

Revised start-up date for Hammerfest LNG

COVID-19 and operational restrictions have pushed the start-up date of the plant to 17 May 2022. ....

Greteb Haaland , Senior Vice President , Thor Johan Haave , Plant Manager , Hammerfest Lng , Liquefied Natural Gas ,

Equinor announces revised Hammerfest LNG start-up date


Advertisement
Based on extensive analyses and mapping of damages, Equinor has updated the schedule for repair and start-up of the LNG plant on Melkøya after the fire on 28 September 2020. Due to the comprehensive scope of work and COVID-19 restrictions, the revised estimated start-up date is set to 31 March 2022.
Even though the fire in September 2020 was limited to the air intake of one of the plant’s five big gas turbines, the fire and firefighting caused substantial damage to the plant.
“We have worked systematically on getting an overview of the damages and scope of work to bring the plant’s technical condition back to the required standard. There is still some uncertainty related to the scope of work, however our best start-up estimate is 31 March 2022, based on current knowledge. Safety is our top priority, and we will not start the plant before it can be done safely,” says Grete B. Haaland, Equinor’s Senior Vice President for Onshore Plants. ....

Greteb Haaland , Senior Vice President , Hammerfest Lng , Liquefied Natural Gas , Flng Plant , Ng Plant Fire , மூத்தவர் துணை ப்ரெஸிடெஂட் ,

Revised Start-Up Date For Hammerfest LNG


Revised Start-Up Date For Hammerfest LNG
Based on extensive analyses and mapping of damages, Equinor has updated the schedule for repair and start-up of the LNG plant on Melkøya after the fire on 28 September 2020. Due to the comprehensive scope of work and Covid-19 restrictions, the revised estimated start-up date is set to 31 March 2022.
Even though the fire in September 2020 was limited to the air intake of one of the plant’s five big gas turbines, the fire and firefighting caused substantial damage to the plant.
“We have worked systematically on getting an overview of the damages and scope of work to bring the plant’s technical condition back to the required standard. There is still some uncertainty related to the scope of work, however our best start-up estimate is 31 March 2022, based on current knowledge. Safety is our top priority, and we will not start the plant before it can be done safely,” says Grete B. Haaland, Equinor’s senior vice president fo ....