Live Breaking News & Updates on Fruitful Hill

Stay updated with breaking news from Fruitful hill. Get real-time updates on events, politics, business, and more. Visit us for reliable news and exclusive interviews.

Fogging schedule for May 10 – 14 - Barbados Today

Fogging schedule for May 10 – 14 - Barbados Today
barbadostoday.bb - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from barbadostoday.bb Daily Mail and Mail on Sunday newspapers.

Bissex , Saint-joseph , Barbados , Bruce-vale , Saint-andrew , Turners-hall , Mount-hillaby , Barbados-general , Belle-plaine , Boarded-hall , Christ-church , Fruitful-hill

Fogging Schedule May 10-14


Social Share
The Vector Control Unit in the Ministry of Health and Wellness will be moving its mosquito eradication exercise to rural parishes this week.
On Monday, May 10, the fogging team will visit the following communities in St Andrew: Hillaby Church Gap, Mose Bottom, Mount Hillaby, Turners Hall and Harewood Road and surrounding areas.
The team will return to St Andrew on Tuesday, May 11, and spray Bawdens Hill, Walkers, Babylon Road, Redman Road, Shorey Village, Douglin Village and environs.
The following day, Wednesday, May 12, fogging will continue in the St Andrew districts of Franklyn Douglin Road, Belmont Road, Worrell Road, Jordan Road, St Simon, Isolation Road, Belleplaine, Lakes Road, Farrell Road, Grecia Road, Corbin Road and surrounding areas. ....

Bissex , Saint-joseph , Barbados , Bruce-vale , Saint-andrew , Turners-hall , Mount-hillaby , Barbados-general , Belle-plaine , Boarded-hall , Christ-church , Fruitful-hill

Road works activities for April 6 – 9 - Barbados Today


Road works activities for April 6 – 9
Article by
April 4, 2021
St James – Along Highway One, the 5 contractors are working diligently to complete the project along the West coast.  Repairs to a 24 feet storm water drain is in progress at Risk Road, after which the road will be paved. At Tulip Drive, St James, paving work will continue this week.
St Andrew – The gabion stabilization project in Trio Path, has been completed. The placement of a footpath from the A. Dacosta Edwards Primary School to the Belleplaine junction continues.
St Joseph – Work on Dark Hole continues this week. The road remains closed in order to facilitate road works and the construction of gabions. Phase 2 of the Fruitful Hill road rehabilitation project is also continuing. Gabion stabilization projects in Bissex, Coconut Grove and Ridge Road are completed and the roads are being reinstated. ....

Belle-plaine , Saint-andrew , Barbados , Fairy-valley , Christ-church , Kendal-hill , Gall-hill , Alexandria , Al-iskandariyah , Egypt , Bissex , Saint-joseph

Road works activities for March 8 – 12 - Barbados Today


Road works activities for March 8 – 12
Article by
March 7, 2021
The paint crew of the Ministry of Transport, Works and Water Resources (MTWW) will recommence painting road markings this week. The crew will be marking the Norman Niles and JTC Roundabouts, weather permitting.
The crew will be working from Monday to Thursday from 6 pm until approximately 4 am. MTWW urges motorists to be extremely careful when traversing the work sites.
St James – Along Highway 1, Infra Construction will be paving from Molyneux to Cemetery Lane. Infra is also milling and paving the stretch of Highway 2A, between Upper Carlton to Rock Dundo. Construction of slipper and kerb is scheduled to commence shortly in Draconia Avenue. ....