An unprecedented amount of infrastructure work is happening across New Orleans altogether more than $500 million on roadways and on vertical construction projects and there is more to come.
For the first time in more than five years, the city has approved nearly $300 million in bonds for a tax-exempt sale, which will lead to multiple projects out for advertisement in the coming months. These projects are designed to improve public spaces, add more stormwater storage and fix more streets.
Additionally, about $110 million in joint infrastructure roadway projects, $10 million in capital building projects, and $100 million in green infrastructure projects will be out for bid in the next few months.
Audubon Group A
After taking a pause during the holidays, Boh Bros Construction Co. crews continued underground utility work and roadway restoration in the Audubon neighborhood as part of the $7.3 million Audubon Group A infrastructure improvement project. In January, crews continued excavation and milling work on Hurst and Octavia streets. Waterline work on Webster and Henry Clay streets continued in close collaboration with Sewerage & Water Board. The project is currently scheduled to be complete in summer 2021, weather permitting.
Black Pearl, East Carrollton Group A
Black Pearl, East Carrollton Group A
The $11.9 million Black Pearl, East Carrollton Group A project, which began construction in August 2020, continues to make progress. In January, Hard Rock Construction Co. completed Americans with Disabilities Act-compliant curb ramps on Burdette, Fern, and Green streets. Waterline and sewer-line work continues on Short and Plum streets. Utility work will continue in the co