NTDC secures Rs6.4bn loan for grid station, transmission lines' construction - Newspaper


According to the MD, the PC-1 cost of the Jhimpir-II transmission lines and substation project is Rs10.753bn whereas the funding required is Rs6.4bn. AFP/File
LAHORE: The National Transmission and Despatch Company (NTDC) on Tuesday secured Rs6.4 billion financing from a three-member consortium of banks for construction of a 220kV/132kV grid station and 35 kilometre-long allied transmission lines for getting 1,274MW of lean renewable energy power from 10 wind energy projects being set up in Gharo-Jhimpir wind corridor near Tando Muhammad Khan in Sindh.
The agreement for the loan, approved by the consortium (National Bank of Pakistan, Habib Bank Limited and Bank Islami Pakistan Limited) was signed by the NTDC Managing Director Muhammad Ayub and the consortium’s representatives Asad Altaf, Zia-ud-Din Tahir and Amir Ashraf at a ceremony held here at Wapda House. ....

Tando Muhammad Khan , Muhammad Ayub , Asad Altaf , V Tando Muhammad Khan , Aamir Ashraf , National Bank , Habib Bank , Lakeside Energy , Indus Wind Energy , National Transmission , Bankislami Pakistan , Modin Energy , Despatch Company , Green Energy , Habib Bank Limited , Bankislami Pakistan Limited , Director Muhammad Ayub , Zia Ud Din Tahir , Gul Ahmed Electric , Metro Wind Power , Liberty Wind Power I , Liberty Wind , Artistic Wind , முஹம்மது அயூப் , அமீர் அஷ்ரஃப் , தேசிய வங்கி ,

NTDC secures Rs6.4b financing


ISLAMABAD:
The National Transmission and Despatch Company (NTDC) has secured a Rs6.4 billion financing facility for the construction of a 220/132-kilovolt sub-station and 35km-long allied transmission lines to evacuate 1,224 megawatts of clean renewable energy from wind power plants at the Jhimpir corridor.
According to a statement released on Tuesday, the financing has been secured from a consortium of local banks.
Speaking at an agreement signing ceremony, NTDC Managing Director Muhammad Ayub said that it was for the first time that NTDC was exploring the option of raising a financial facility from its own resources (balance sheet) without government guarantee.
“Previously, the company had relied on government of Pakistan’s guaranteed loans from the local market,” he said. “This facility will be a precursor to more funding for the upcoming NTDC projects.” ....

Safdar Ali , North West Frontier , Muhammad Ayub , Wasim Saadat , Despatch Company , National Transmission , Director Muhammad Ayub , Managing Director Safdar Ali , Chief Financial Officer Wasim Saadat , சஃப்தார் அலி , வடக்கு மேற்கு எல்லை , முஹம்மது அயூப் , அனுப்புதல் நிறுவனம் , தேசிய பரவும் முறை ,

Torkham-Nowshera power line to be laid by next year: NTDC - Newspaper


LAHORE: The National Trans­mis­sion and Despatch Company (NTDC) has said that it will complete the laying of 500kV High Voltage Direct Current (HVDC) transmission line from Torkham border to Nowshera by December 2022, as well as construction of a convertor station.
The line is meant to receive 1,000 megawatts from Kyrgyzstan in direct current (DC), convert it at the convertor station in Nowshera (Azakhel Bala) and add it to the national grid to meet the summer demand of Pakistan under the Central Asia-South Asia power project commonly known as CASA-1000.
HVDC will receive 1,000MW from Kyrgyzstan
“We are hopeful that we will complete our portion of the HVDC line by November 2022, a month before our deadline. Similarly, we are also making efforts to complete the convertor station by December 2023 instead of June 2024,” a senior official told Dawn after the NTDC management established a camp office at Azakhel Bala to fast-track the work. ....

Azakhel Bala , North West Frontier , Muhammad Ayub , Asia South , Nowshera Azakhel Bala , Islamic Development Bank , Despatch Company , National Trans , World Bank , Central Asia South , Khyber Pakhtunkhwa , Director Muhammad Ayub , வடக்கு மேற்கு எல்லை , முஹம்மது அயூப் , ஆசியா தெற்கு , இஸ்லாமிய வளர்ச்சி வங்கி , அனுப்புதல் நிறுவனம் , தேசிய டிரான்ஸ் , உலகம் வங்கி , மைய ஆசியா தெற்கு , கைபர் பக்துங்க்வ ,

NTDC starts work on transmission line for Suki Kinari project


NTDC starts work on transmission line for Suki Kinari project
Will connect transmission with 500 kV Neelum-Jhelum transmission line
PHOTO: REUTERS
ISLAMABAD:
The National Transmission and Despatch Company (NTDC) has started construction of 75-kilometer-long 500 kV double circuit transmission line for evacuation of power from 870MW Suki Kinari Hydropower Project.
The transmission will be connected with 500 kV Neelum-Jhelum transmission line. NTDC has completed basic works like survey and soil investigation, route validation, demarcation of forest trees, approach and access roads etc.
NTDC Managing Director Muhammad Ayub inaugurated the construction works for the first tower of the said transmission line at Garhi Habibullah, Kyber-Pakhtunkhwa. He directed the NTDC teams and contractor to complete the project before its deadline. The NTDC MD also planted a tree at the power house of Suki Kinari hydropower plant as part of ongoing tree plantation campaign of N ....

Garhi Habibullah , North West Frontier , Muhammad Ayub , Azad Kashmir , Despatch Company , National Transmission , Asian Development Bank , Public Sector Development Programme , Director Muhammad Ayub , Suki Kinari , கர்தி ஹபிபுல்லா , வடக்கு மேற்கு எல்லை , முஹம்மது அயூப் , அசாத் காஷ்மீர் , அனுப்புதல் நிறுவனம் , தேசிய பரவும் முறை , ஆசிய வளர்ச்சி வங்கி , பொது துறை வளர்ச்சி ப்ரோக்ராம் , சுக்கி கிணரி ,