Bureaucratic hurdles: KP's four hydropower projects delayed by three years


August 4, 2021
PESHAWAR: Khyber Pakhtunkhwa’s four 244.4 MW renewable and cheap electricity hydropower projects are stalled due to negligence of the Ministry of Energy (Power Division) and PESCO for the last three years.
The projects are pending due to non-approval, notification, import certificates, and purchase agreement. Similarly, Pakhtunkhwa Energy and Development Organisation (PEDO) has an arrear of Rs7,147.604 million in electricity sales to the federal government. A reliable government source told this correspondent that the projects were delayed due to bureaucratic hurdles, which are hampering the production of cheap electricity, while Prime Minister Imran Khan is focusing on cheap hydropower generation in the country. Ongoing hydropower projects are also being affected due to non-payment of dues. ....

North West Frontier , Arkari Gol , Daral Khwar , Daral Khawar , Imran Khan , Muhammad Naeem , Pakhtunkhwa Energy , Peshawar High Court , Ministry Of Energy Power Division , Ministry Of Energy , Saifco Energy , Power Division , Development Organisation , Central Power Purchasing Agency , Khyber Pakhtunkhwa , Prime Minister Imran Khan , Master Hydro , Official Gazette , Fifth Schedule Custom Act , Power Project , Executive Muhammad Naeem , வடக்கு மேற்கு எல்லை , தாராள கவர் , இம்ரான் காந் , முஹம்மது ந்ஈம் , பக்துங்க்வ ஆற்றல் ,

Bureaucratic hurdles: KP's four hydropower projects delayed for three years


August 4, 2021
PESHAWAR: Khyber Pakhtunkhwa’s four 244.4 MW renewable and cheap electricity hydropower projects are stalled due to negligence of the Ministry of Energy (Power Division) and PESCO for the last three years.
The projects are pending due to non-approval, notification, import certificates, and purchase agreement. Similarly, Pakhtunkhwa Energy and Development Organisation (PEDO) has an arrear of Rs7,147.604 million in electricity sales to the federal government.
A reliable government source told this correspondent that the projects were delayed due to bureaucratic hurdles, which are hampering the production of cheap electricity, while Prime Minister Imran Khan is focusing on cheap hydropower generation in the country. Ongoing hydropower projects are also being affected due to non-payment of dues. ....

North West Frontier , Arkari Gol , Daral Khwar , Daral Khawar , Imran Khan , Muhammad Naeem , Pakhtunkhwa Energy , Peshawar High Court , Ministry Of Energy Power Division , Ministry Of Energy , Saifco Energy , Power Division , Development Organisation , Central Power Purchasing Agency , Khyber Pakhtunkhwa , Prime Minister Imran Khan , Master Hydro , Official Gazette , Fifth Schedule Custom Act , Power Project , Executive Muhammad Naeem , வடக்கு மேற்கு எல்லை , தாராள கவர் , இம்ரான் காந் , முஹம்மது ந்ஈம் , பக்துங்க்வ ஆற்றல் ,

Time to expedite work on hydropower projects to address energy crisis


Daily Times
July 12, 2021
Amid sizzling temperature of above 40 degree centigrade coupled with long hours, unannounced power outages have started adversely affecting people and industrial production owing to a substantial energy shortfall of about 600 megawatt in Khyber Pakhtunkhwa gripped by severe heat wave since the start of this month.
As sun is spewing out severe heat, people in Peshawar’s peripheries, southern districts including Bannu and Dera Ismail Khan besides merged areas were witnessing the brunt of
load-shedding for about 10-14 hours daily, especially on high loss feeders forcing consumers to install solar systems, purchase generators and UPS besides water pools to protect their loved ones from the scorching heat. ....

North West Frontier , Dheri Ishaq , South Korea , Dera Ismail Khan , Daral Khawar , Daral Khwar , Malik Muhammad Luqman , Diamer Bhasha , Capri Charkhel , Shamsul Mulk , Access To Clean Energy Investment Program , Nuclear Power Company , World Bank , Pakhtunkhwa Energy Development Organization , Asian Development Bank , Power Development Authority Wapda , International Finance Corporation , National Power Control System , Committee Of National Economic Council , Khyber Pakhtunkhwa , Misal Khan , Information Officer , Distribution Circle , Former Water , Power Development Authority , Engr Malik Muhammad Luqman ,