(Minneapolis, MN) As students return to the U-of-M’s Minneapolis campus, officials say they’ve expanded monitoring of sanitary sewers for flammable substances. It’s prompted by an underground explosion June 30th that blew
The program evaluation from her office indicates there have been 658 construction "change orders" totaling nearly $220 million. At a current estimate of $2.7 billion, the project is nearly $1.5 billion over its original budget of $1.25 billion.
Metropolitan Council Chairman Charlie Zelle says he'll know by the end of this year how his agency will make up a $534 million funding gap for Southwest Light Rail.