Progress Update: Dedicated Lanes for Cebu Bus Rapid Transit (CBRT) to be Completed Before Sinulog
THE dedicated lanes for the first package of the Cebu Bus Rapid Transit (CBRT) are 80 percent finished, and should be fully completed by Jan. 15, 2024, or before the celebration of the Fiesta SeƱor and the Sinulog.
Related Keywords
China ,
Ferdinand Marcos Jr ,
Norvin Imbong ,
Construction Group Co ,
World Bank ,
Cebu Bus Rapid Transit ,
Cebu South Bus Terminal ,
Sunstar Cebu ,
Cebu City ,
Shuman Road ,
Bridge Construction Group ,
President Ferdinand Marcos ,
Gorordo Ave ,
Archbishop Reyes ,
South Road Properties ,
Cebu Bus Rapid Transit Cbrt ,
Dedicated Lanes 80 Complete ,
Completion By Jan 15 ,
024 ,
Fiesta Senor And Sinulog Deadline ,
Initial Target Missed Due To Delays ,
Bus Stations To Be Built Soon ,
Drainage System 20 Finished ,
Procurement For Package 2 Starts In January ,
Market Sounding Underway ,
Bidding Documents For Package 2 Sent To World Bank ,