Slovenian power supplier HSE said Thursday it has reached an out-of-court settlement with US giant General Electric over alleged irregularities in the construction of a much-delayed coal-fired power plant outside Ljubljana
Ljubljana, (APP - UrduPoint / Pakistan Point News - 11th Mar, 2021 ) :Slovenian power supplier HSE said Thursday it has reached an out-of-court settlement with US giant General Electric over alleged irregularities in the construction of a much-delayed coal-fired power plant outside Ljubljana.
HSE said in a statement that GE had agreed to pay 261 millionEuros ($310 million) to settle a dispute over the TES 6 unit at the coal power plant in Sostanj, some 80 kilometres (50 miles) northeast of the capital.

Related Keywords

Ljubljana , Slovenia General , Slovenia , Krsko , Kr Ko , France , Sostanj , O Tanj , French , Slovenian , Frank Lehmann , Josef Reisel , Alstom , General Electric , Pakistan Point News , , ஸ்லோவேனியா ஜநரல் , ஸ்லோவேனியா , க்ர் கோ , பிரான்ஸ் , பிரஞ்சு , ஸ்லோவேனியன் , வெளிப்படையான லெஹ்மன் , ஆஸ்டோம் , ஜநரல் மின்சார , பாக்கிஸ்தான் பாயஂட் செய்தி ,

© 2025 Vimarsana