Drawdown Begins at Edenville Dam Complex : comparemela.com

Drawdown Begins at Edenville Dam Complex


9 & 10 News
February 24, 2021
Construction crews began a drawdown of the Tobacco River spillway in Gladwin County on Wednesday.
The drawdown is a critical step in progressing with repairs and helping the Mid-Michigan area recover from historic flooding.
Back in may an overtopping of the Edenville Dam and failure of the Sanford Dam led to the devastating floods.
Homes and businesses were wiped away and the floods caused millions of dollars in damage.
Water flowed through the Edenville Dam complex Wednesday morning for the first time since May’s flooding.
“What you’re going to see is a slow dewatering process. Approximately 1 foot per day is going to be lowered from the upstream side to allow equalization of pressure and again to take the pressure off the other side of the Tittabawassee River, the M-30 bridge project,” said Dave Helmstetter, Construction Manager with AECOM.

Related Keywords

Gladwin County , Michigan , United States , Tittabawassee River , Tobacco River , Edenville Dam , Dave Helmstetter , Karen Moore , Gladwin County Commission , , Sanford Dam , Construction Manager , Gladwin County Commission Chair Karen , கிளாட்வின் கவுண்டி , மிச்சிகன் , ஒன்றுபட்டது மாநிலங்களில் , திட்தாபவஸ்ஸீ நதி , புகையிலை நதி , எடன்வில்லே அணை , டேவ் ஹெல்ம்ஸ்டெட்டர் , கரேன் மூர் , கிளாட்வின் கவுண்டி தரகு , சான்ஃபோர்ட் அணை , கட்டுமானம் மேலாளர் , கிளாட்வின் கவுண்டி தரகு நாற்காலி கரேன் ,