McCarthy wraps up rehabilitation of Port Houston Wharf 3 April 9, 2021, by Eldin Ganic
McCarthy Building Companies, Inc. has successfully completed rehabilitation construction on Wharf 3 within Barbours Cut Container Terminal at Port Houston, located in LaPorte, Texas.
The project, part of the Port’s continued effort to grow and modernize, is set to increase the facilities efficiency and capacity.
The Wharf 3 project included three scopes of work.
First, the rehabilitation of Wharf 3, which consisted of the reconstruction of 1,000 feet of the wharf, dredging, drilled shafts, fenders, bollards, crane rail, concrete paving, stevedore support building, electric and telecommunications.
Second was construction of the electrical infrastructure, which includes 3,600 feet of underground duct bank, concrete paving, jack and bore and directional drilling, as well as electric and telecommunications.