comparemela.com


McCarthy wraps up rehabilitation of Port Houston Wharf 3
April 9, 2021,
by
Eldin Ganic
McCarthy Building Companies, Inc. has successfully completed rehabilitation construction on Wharf 3 within Barbours Cut Container Terminal at Port Houston, located in LaPorte, Texas.
The project, part of the Port’s continued effort to grow and modernize, is set to increase the facilities efficiency and capacity.
The Wharf 3 project included three scopes of work.
First, the rehabilitation of Wharf 3, which consisted of the reconstruction of 1,000 feet of the wharf, dredging, drilled shafts, fenders, bollards, crane rail, concrete paving, stevedore support building, electric and telecommunications.
Second was construction of the electrical infrastructure, which includes 3,600 feet of underground duct bank, concrete paving, jack and bore and directional drilling, as well as electric and telecommunications.

Related Keywords

Barbours Cut ,Texas ,United States , ,Mccarthy Building Companies Inc ,Mccarthy Building Companies ,Barbours Cut Container Terminal ,Port Houston ,Lash Dock ,Container Yard ,Bayport Container Terminal ,பார்போர்ஸ் வெட்டு ,டெக்சாஸ் ,ஒன்றுபட்டது மாநிலங்களில் ,ம்க்கார்தீ கட்டிடம் நிறுவனங்கள் இன்க் ,ம்க்கார்தீ கட்டிடம் நிறுவனங்கள் ,பார்போர்ஸ் வெட்டு கொள்கலன் முனையத்தில் ,போர்த் ஹூஸ்டன் ,கொள்கலன் முற்றத்தில் ,வளைகுடா கொள்கலன் முனையத்தில் ,

© 2024 Vimarsana

comparemela.com © 2020. All Rights Reserved.