Rourkela’s smart road project runs into incomplete sewerage system
The sewerage system covering 231 km is being executed since early 2017 at a cost of Rs 340.20 crore including five years maintenance cost.
Share Via Email
| A+A A- By Express News Service
ROURKELA: Incomplete sewerage works have emerged as a roadblock to the administration’s efforts to complete smart road projects and beautification plans in the Steel City well ahead of the Men’s Hockey World Cup 2023. Roads lying damaged for years due to ongoing underground sewerage system continue to torment the citizens besides delaying the smart road project of Rourkela Smart City Ltd (RSCL).