Maine South High School
PROJECT SUMMARY
Current Progress
Maine East: Field House windows are wrapping up which makes the addition weather tight. Mechanical, electrical, plumbing and fire protection trades are ongoing on both floors of the addition. 1st floor is substantially roughed in and ceiling system / finishes are commencing. Progress continues to maintain schedule.
The Potter Wing renovation project has been turned over to the District. Punch List activities are underway.
The 2nd portion of 3rd floor C wing is wrapping up and will be turned over for District’s use after the 1st of the year.
District has vacated the Center Court area and Abatement is on going on all levels. Work / Demolition will commence once abatement is completed.
Maine South High School
PROJECT SUMMARY
Summer Construction 2020
Continue to complete punch list activities, commissioning and close out documents at each school currently. Progress of ongoing work by school is listed below.
Maine East: Field House Brick Veneer is wrapping up. Windows and exterior glazing will commence over the next few weeks. Mechanical, electrical, plumbing and fire protection trades have all started work inside the addition. Progress continues to maintain schedule.
The Potter Wing renovation project is being wrapped up. Final details and punch listing is on going. Owner has commenced their move in process which will continue over the next several weeks.