comparemela.com

Latest Breaking News On - பரவும் முறை நிறுவனம் ஆஃப் தெலுங்கானா லிமிடெட் - Page 1 : comparemela.com

SCCL Yellandu plant synced with grid

SCCL Yellandu plant synced with grid Updated: Updated: March 06, 2021 23:23 IST 39 MW plant established as part of plans to set up 300 MW capacity solar plants across mining areas Share Article AAA Directors of SCCL S. Chandrasekhar and D. Satynarayana along with other officials at the synchronisation of the 39 MW solar plant of the company with the grid at Yellandu in Bhadradri-Kothagudem   39 MW plant established as part of plans to set up 300 MW capacity solar plants across mining areas The 39 megawatt solar power plant established by the Singareni Collieries Company Ltd (SCCL) at Yellandu in Bhadradri-Kothagudem was synchronised with the grid by two directors of the coal company at Yellandu on Saturday.

Energy consumption reaches new high, clocks 261 MU on Friday

Energy consumption reaches new high, clocks 261 MU on Friday Updated: Updated: February 28, 2021 00:27 IST Peak load of power on the system also records highest at 13,452 MW on the day Share Article AAA Peak load of power on the system also records highest at 13,452 MW on the day As expected, the consumption of energy in the State is on a steady increase along with the rising mercury level and it has clocked a record 260.98 million units (MU) on Friday with the agriculture and domestic sectors pulling up the demand. The day also witnessed the highest ever peak load of power on the transmission system in the State when it touched 13,452 megawatt at 8.31 a.m. on Friday, surpassing the previous peak load of 13,252 MW recorded on January 30. The previous highest energy consumption was recorded on March 18 last year, when it clocked at 256.18 MU. On February 25 (Thursday) the consumption came close to the previous record but remained at 256.04 MU.

Pact for open access to Manuguru solar power

Pact for open access to Manuguru solar power Updated: Updated: Agreement with Transco, discom Agreement with Transco, discom A tripartite agreement on the open access to solar power generated in Manuguru area by Singareni Collieries Company Ltd (SCCL) was signed on Friday between SCCL, Transmission Corporation of Telangana Ltd (TS-Transco) and Northern Power Distribution Company of Telangana Ltd (TSNPDCL). The agreement enables SCCL to avail the solar power generated in the 30 megawatt Manuguru area plant for its needs in Manuguru and Illendu areas through transmission and distribution lines of TS-Transco and the Northern Discom and the purchase of the remaining power by the discom.

© 2025 Vimarsana

vimarsana © 2020. All Rights Reserved.