Advertisement
En+ Group, a producer of low-carbon aluminium and one of the largest private sector generators of hydropower, has announced that it has begun the replacement of six hydraulic units at the Group’s Bratsk HPP (hydropower plant) as part of its large-scale ‘New Energy’ modernisation programme. The total investment in the project for this stage of the project is more than 1.5 billion roubles. The replacement works are planned to take place from 2021 to 2026. The outcome of the works will see all 18 impellers replaced (12 have already been replaced during the earlier stages of the modernisation programme in 2007 - 2010 and 2014 - 2017).