The second phase of a €3.1 million project to regenerate Senglea is under way, Infrastructure Minister Ian Borg announced on Thursday.
Speaking during a visit to the city, he said works had begun on Piazza Giorgio Mitrovich through an investment of €1.8 million.
It follows from the first phase of the project, which was a €1.3 million restoration and embellishment of the Senglea Gate.
The entire project started in April 2020 and was the first phase was due to be finished at the end of the year.
Phase one included some 5,800 metres of fortification walls, two tunnels, a clock tower, a belvedere and the replacement of a primary school wall.