Work on road underbridge set for completion in record time
Updated:
Updated:
Hubballi Division of South Western Railway is building it at Londa
Share Article
AAA
The Hubballi Division of South Western Railway is all set to complete construction of a road underbridge at Londa Station Yard in less than 90 days.
Hubballi Division of South Western Railway is building it at Londa
In a record of sorts in the Indian Railways, the Hubballi Division of South Western Railway (SWR) is all set to complete the construction of a road underbridge in less than 90 days.
According to a press release issued by the Hubballi Division, proper planning and coordination by the engineering team of Hubballi Division has helped in the early completion of the structure at Londa Station Yard, in less than 90 days, which, otherwise, would have taken over 20 months.