Dubai Electricity and Water Authority (Dewa) has announced that the Hassyan Power Complex, which was recently converted from clean coal to gas, added 1,200 MW to its current production capacity. A further 1200 MW will be added in phases by Q3 2023.
Dubai Electricity and Water Authority (Dewa) has confirmed that the current production capacity of Hassyan Power Complex reached 1,200 megawatts (MW), using the Independent Power Producer (IPP) model.
Dubai Electricity and Water Authority (DEWA) has confirmed that the current production capacity of Hassyan Power Complex reached 1,200 megawatts (MW), using the Independent Power Producer (IPP) model. A further 600 MW will be added in Q4 of 2022, and an additional 600 MW will be added by Q3 of 2023. ..