Since the Walyering gas field was sanctioned for development in mid-August the Walyering EP447 JV has entered into the execution phase and has made good progress across a number of key project fronts.
Strike Energy has announced that the Walyering gas field has been sanctioned for development in only 9 months from its announced discovery. Commissioning gas is expected to enter the upstream facility by the end of CY22 with first gas sales targeted in Q1/23.
Strike Energy has released the maiden independently certified Reserves & Resources report for the Walyering gas field procured for the EP447 JV. Strike intends to shortly engage with the EP447 JV to contemplate a final investment decision given the proposed development has successfully passed through its primary environmental review process.