Australia: Vintage Energy announces operations update
04 Feb 2021
PEL 155: Nangwarry-1 testing planned for mid to late February 2021
ATP 2021: Non-binding rig LOI to drill Vali-2; Vali-1ST1 to be completed with upcoming wells; flowline equipment purchase deferred to incorporate well results and evaluation of upside potential; joint gas marketing approved by ACCC
PRL 211: Non-binding rig LOI to drill Odin-1
Cervantes: Non-binding rig LOI to drill Cervantes-1, contract being negotiated
Vintage Energy has provided an update on activities relating to the testing of
Nangwarry-1 in the onshore Otway Basin, the
Vali gas field and
Cervantes prospect in the Perth Basin.
Otway Basin - PEL 155 (Vintage 50%, Otway Energy 50% and operator)
Moomba
Queensland
Australia
Perth-basin
Western-australia
Nappamerri
Vali-fieldas
Neil-gibbins
Metgasco-ltd
Schlumberger
Senex-energy
Stuart-petroleum
Vintage Energy Ltd (ASX:VEN) Operations Update
Operations UpdateMelbourne, Feb 5, 2021 AEST (ABN Newswire) - Vintage Energy Ltd (
ASX:VEN) provides an update on activities relating to the testing of Nangwarry-1 in the onshore Otway Basin, the Vali gas field and Odin prospect in the Cooper Basin and the Cervantes prospect in the Perth Basin.
Otway Basin - PEL 155 (Vintage 50%, Otway Energy Pty Ltd 50% and operator)
The procurement of long lead items for the testing of Nangwarry-1 is nearly complete. These items, along with the Superior Energy rig, will be mobilised to site around the middle of February 2021, with testing of Nangwarry-1 to commence soon thereafter.
Moomba
Queensland
Australia
Melbourne
Victoria
Perth-basin
Western-australia
Nappamerri
Neil-gibbins
Otway-energy-pty-ltd
Schlumberger
Energy-ltd
Vintage Energy Ltd (ASX:VEN) Quarterly Activity - Cashflow Report
Quarterly Activity - Cashflow ReportMelbourne, Jan 29, 2021 AEST (ABN Newswire) - FEED for the Vali-1 ST1 connection to the Beckler Field (which is connected to the Dullingari facilities and ultimately Moomba) was awarded to GPA Engineering. The main objective of the now completed FEED phase was to complete the necessary engineering to identify long lead items and refine the cost estimate for a final investment decision, which will then initiate the procurement stage.
To maximise value from the Vali gas field, through increased production and resultant cash flow, further wells are planned. To this end, potential locations for further drilling in the field have been identified and are under discussion within the joint venture, with rig scouting for these wells underway. The development concept for the Vali gas field (refer ASX release dated 17 September 2020) identified that up to nine fracture stimulated ve
Moomba
Queensland
Australia
Melbourne
Victoria
Nappamerri
Nappamerri-group
Equipoise-pte-ltd
Energy-ltd
Quarterly-activity
Beckler-field
vimarsana © 2020. All Rights Reserved.