HOT SPRINGS Action the Hot Springs Board of Directors took last week intends to hold the line on costs for the water treatment plant the city is building off Amity Road.
Leveraging the 60-foot difference in elevation between Lake Ouachita and south Garland County, the city will gravity flow water from the lake to the new treatment plant it's building on Little Mazarn Road.
Leveraging the 60-foot difference in elevation between Lake Ouachita and south Garland County, the city will gravity flow water from the lake to the new treatment plant it's building on Little Mazarn Road.
The $9,167,669 contract the Hot Springs Board of Directors awarded Belt Construction Inc. on Tuesday night puts under contract all of the overland route for the Lake Ouachita water supply project's raw waterline.
The $9,167,669 contract the Hot Springs Board of Directors awarded Belt Construction Inc. on Tuesday night puts under contract all of the overland route for the Lake Ouachita water supply project's raw waterline.