Crews Rebuild I-410: Southwest Improvement Project : CEG

Tue January 26, 2021 - West Edition #3 Irwin Rapoport – CEG Correspondent Progress is being made on the two flyover ramps – one lane and approximately 3,500 ft. long — with both flyovers on schedule for completion in 2021. Phase 1 of the I-410 Southwest improvement project in San Antonio, being constructed by Williams Brothers Construction Co. Inc. (WBC), began in fall 2019 and is expected to be delivered by 2022, with the direct connectors to be ready in 2021. The $78 million contract involves adding one lane in each direction from U.S. 90 to Ingram Road (6.3 mi.), which is currently three lanes in each direction, and constructing two flyover ramps at the SH 151 interchange. The work also includes the installation of drainage infrastructure and electrical systems signal and intelligent transportation systems (ITS).