Additionally, according to FDOT, the project includes upgrading pedestrian crossings at the three signalized intersections along the project route to bring them into compliance with the Americans with Disabilities Act, along with drainage improvements and improvements to the traffic signals at the Mack Bayou Road, Hewett Road and CR 30A intersections.
The work is scheduled for completion in late 2023, according to the FDOT.
The work now beginning to wind down on U.S. 98 in Walton County is a $42 million project that had been scheduled for completion this summer, but a more recent FDOT schedule placed the projected completion date this fall.