The Warwick School Committee learned Tuesday that planning for new Pilgrim and Toll Gate High Schools are on schedule from Chris Spiegel, senior project manager at LeftField Project Management based …
Warwick School Committee took action on multiple financial matters, including the school’s lunch money debt and layoffs of teachers under consideration Tuesday. The committee approved the …
As a result of action taken Thursday, Warwick Independent School Employees (WISE) have a new 3-year contract; Warwick teachers will similarly have a 3-year contract if the membership approve the …
Timetable to groundbreaking for new high schools Feb 13 - retention of OPM Mid April - complete design for bid docs Late April - Out to bid for design build contractors Late May, early June - …