With Hawley broadband setup nearing completion, officials focus on connecting residents
Related stories
HAWLEY The Florida, Hawley, Monroe and Savoy (FHMS) broadband buildout moved into the fourth phase of a five-phase plan in December, and officials are focusing on connecting residents as quickly as possible.
According to FHMS Broadband Network Committee Chair Kirby “Lark” Thwing, Phase 3 was completed on Dec. 18, building the necessary infrastructure in Hawley on Forget Road near Sidehill Farm, Stetson Road, West Hawley Road near Savoy Road, Forge Hollow Road and near 129 East Hawley Road. Other sites within Hawley have been operational for a few months now.