Room to connect the new paths running along the outer edge of the deck scheduled to open tuesday, at noon. At Yerba Buena Island tunnel new road surface being prepared by this morning, the upper deck finished and lower more than half done. Paving will complete tomorrow on a temporary onramp from the islandw rq grinding, paving and striping is a big problem, 1. 2 major square feet and only 14,000 tons will be brought in to pay. Last update is that everything is looking really good. Weve got great weather. So were confident how things are going so far. There are 400 workers on the bridge working in shifts 24 hours per day aiming for the scheduled tuesday 5 00 a. M. Opening. A lot of people here are putting in very long hours. Everyone, including contractors are abiding by worker safety laws. So this grinding here started immediately after the closure last night grinding is what it sounds like, its tearing up asphalt about two inches here, theyre repaving arv a good new road service there